Zorro Development Corp - Project Report 10/04/
21- MICROWAVE & START ENQ
13
EST.COST 1 NOTES
a PHOTO STATUS
7/13—JE requested to investigate Microwave option
Awaiti
5/9/13 — Existing Microwave details forwarded to JE, RK & JR
Direction
16/13 — JE requested contacting Dava Baumann reference
on E Mall
delivery of service from Sandia Crest verses D Mark
dated
5/17/13 — Dave Baumann forwarded details of RSM — Craig
09/27/13
Franck. Brice has been in contct with Craig
5/24/13 — Received bid from Southwestern Wireless, have call
set up for 5/28/13 to review bid
5/31/13 — Forwarded update of Project to JE, RK & JR
13 — Forwarded TW Telecom proposal for Delivery of Service
JE & RK Firm bids due 6/14/13
6/14/13 — Received bid from Southwestern Wireless confirming
details. Informed JE, wiN forward once all details confirmed
6/20/13 — JE approved Southwestern Wireless bid.
RK to negotiate final bid
6/27/13 — Southwestern Wireless unable to deliver bundled T1
8/13 — Looking into other options
7/12/13 — Awaiting proposal from Advanced Communcations
Will review proposed Link Plan with JE on site
8/14/13 — Proposal received
— Conference call completed with RK, BG, SD & RB
7/13 — Advanced Communcations on site to review Projec
t JE
8/18/13 —Confirming Advanced Communcations require Servic
e
Provider before their can engineer final solution
8/26/13 — Filed a complaint with PRC NM regarding Century Link
backing out of Service Provider option. 10 days to respond
7/13 — Contacted Steven Grabiel (High Speed Internet
Edgewood) Expect Proposal 8/6/13. Will forward once in hand
8/29/13 — Received Proposal from RMC for x 3 40ft poles
Page 1
EFTA01124735
Zorro Development Corp - Project Report 10/04/13
9/17/13 — Received Proposal from High Speed Internet
$500.00 per mth for 10 mbps plus $10000.00 to run Ethernet
Cable to Tele Beeper shed on Sandia Crest
Approval JE 9/19/13 — JE approved site visit by HugesNet
9/20/13 — Have forwarded info to HugesNet, awaiting installation
date. Order #5709982. Once Installation Is complete & account
active, final details of package will be added.
9/23/13 — Received proposal from Advanced Communcations
on upgrading Router & Wireless Links to RC & Lodge
9/27/17 - Forwarded to RK & DI proposals from RMC Electric
& Advanced Communcations.. Awaiting direction
9/30/13 — HugesNet due on site
10/2/13 — Postponed HugesNet until direction provided
Page 2
EFTA01124736
Zorro Development Corp- Project Report 10/
{??-LANDSCAPING , START END
04/13
EST.COST NOTES
MII PHOTO STATUS i
06/01/13 $75,000.00 3/28/13 — Refurbishment & Mainteance Proposals
from 3 Awaiting
companies forwarded to RK & DI
Anoroval JE Direction
7/13 — JE approved Aspen for Refurbishment Project & Aspen
on
to remain as ZDC Mainteance Company
E Malls
5/9/13 — New Pro !forwarded to JE, RK awaitin • direction dated
5/16/13 — Final forwarded to RK 08/22113
5/24/13 — Aspen agreed to $75,000.00
09128/13
5/31/13 - of $44,383.08 issued to 09/27/13
1/13 — Project Started
6/8/13 — Work continues, soil preperatlon in progess
14/13 — Plant material starting to arrive
6/18/13 — More plant materall on site
6/21/13 — Back Parking Area - Planting & Irrigation Complete
6/22/13 — Plantin & I n continues —attached • otos
026/13 — More plant material on site
172 7/13 — Preparation of front parking area begins, Columbines
Trumpert Vine planted along pathway between MH & Dog Pen
Irrigation installed In all panted areas — attached photos
7/12/13 — Plant & Irrigation installation continues —
Attached • lent schedule & • hotos
7/26/13 — Project 90% Complete
Havin issues locating Cypress Trees.
8/7/13 — JE decided not to install Cypress Trees, in Aspen will
rernove 4 old Henvthoms & re with 4 Jun
8/9/13 — Final Breakdown of P forwarded to JE
10/13 —JE to meet Jose from Aspen to review Project
11/13 — JE updated request — remove old Hawthorns & Junipers
8/22/13 — Forwarded to JE sum ted colourful t material,
selected for discussed areas — awaiting direction
Page 3
EFTA01124737
Zorro Development Corp - Project Report 10/
04/13
'8/24/13 — Awaiting Proposals - 3 vendors for Preventive Spray
ing
iri Fertilizing of new & exisiting plant material due by 9/24/1
3
9/18/13 — Aspen Landscaping removed old Hawthorns &
Junipers
attached photos
9/22/13 — Awaiting Direction
9/26/13 — Forwarded to RK 3 Proposals for Preventive Spray
ing
Fertilizing
9/27/13 — Forwarded to JE & RK photo of proposed Blue
Spruce
6 — 7 ft, larger would be available in the Spring — attach
ed photo
10/4/13 — Awaiting direction
Page 4
EFTA01124738
Zorro Development Corp - Project Report 10/
122A - LANDSCAPE START END
04/13
gST.COST- NOTES
LIGHTING PHOTO STATUS
4/27/13 — JE Approved New Landscape Lighting
5/1/13 — Unable to move forward until Project 22 — Landscaping
has been resolved
8/1/13 — Reviewing with Aspen about plant location
7/18/13 — Have installed Lighting where planting is complete
7/27/13 — Before proceeding will review with JE on site
8/22/13 — Will Complete Project once Project 22 — Landscaping
MH Complete
Page 5
EFTA01124739
Zorro Development Corp- Project Repor 10/
22Ø IN HOUSE - START END
t 04/13
! EST.COST NOTES
LANDSCAPING PHOTO STATUS
06/03/13 4/27/13 —JE Approved, removal of dead Pine in courtyard,
removal of Ponderosa Pines, Landscape Lighting at front
Enterance & to relocate Pinons to the area
6/3/13 — Project Started
6/18/13 — Removal of Pine & Ponderosa Pine complete -
attached photos
7/19/13 — Relocation/Installation of Pinons from remot
e areas of
the Ranch to front enterance continues
7/27/13 — Project 90% complete, will review with JE while on
site
8/21/13 — Reviewed area with JE, outlining scope of work
8/29/13 - Removal of dead & infected Pinions — Comp
lete
9/18/13 — Forwarded to JE & RK estimate — hand dug & plant
Pinions by Aspen Landscaping $375.00 per tree
To purchase & plant locally 8ft to1Oft trees $150.00 per tree
Estmated number of trees, MH —12, LV —14
9/22/13 —Awaiting Direction
Aooroval JE
$5,040.00 9/24/13 — JE Approved purchase of local Pinions
at $150.00 per
tree, awaiting proposal due 9/30/13
9130/13 — Received proposal, reviewing with vendor
10/2/13 — Forward Proposal to JE & RK
10/3/13 — Working with Vendor to schedule start date
y4— MEDIA ROOM START END EST.COST
CURTAINS NOTES PHOTO STATUS
Blackout & Rings $6,262.08 4/27/13 - JE Selected Fabric for Project
5/10/13 — Project Request Form forwarded to JE & RK Awaiting
5/17/13 — Resubmitted Project Request Form to JE Direction
5/31/13 — As of date Awaiting Direction
Page 6
EFTA01124740
Zorro Development Corp - Project Report 10/
6 — OFFICE 04/13
START 2112 EST.COST NOTES
CURTAINS PHOTO ,STATUS
Lined & Rings $2,527.01 4/27/13 -JE Selected Fabric for Project
Awaiting
5/2/13 — Vendors & Manufacturer enable to provide enoujh
Direction
yardage of selected fabric
on
5/9/13 —Mother fabric option forwarded to JE
Forwarded
5/10/13 —Project Request Form forwarded to JE & RK
E Mail
5/17/13 — Resubmitted Project Request Form to JE
dated
5/31/13 — As of date Awaiting Direction
05/17/13
Page 7
EFTA01124741
Zorro Development Corp - Project Report 10/
27 - TERRACES START END
04/13
- EST.COST NOTES
Terraces - $52,000.00 04107/13 PHOTO STATUS
$56,200.00 12/12/12 — Bid received.
Stucco/Gutters/Painting Awaiting
3/20/13 — JE Approved Bid
$4,200.00 Proposal
4/7/13 — Project Started
from
4/20/13 — Libary Membrane installed
3 B's
5/10/13 — Change Order Submitted by Vendor $2,700.00 +
tax
5/16/13 — MBR Balustrade reinstalled
5/20113 — MBR Membrane to be installed
5/31/13 — A fault in 1roll of material, vendor has reordered
6/14/13 — Membranes & Gutters Complete — attached photo
s
6/21/13 — Stucco & Painting Complete — attached photos
6/24/13 — Final review on completed work with Vendor
7/2J13 — Final Punch Out to begin of all outstanding work
7/3/13 — Project Complete on Telescope Terrace
8/8/13 —JE requested carpet to be installed on both terraces
Carpet - $2,078.15 8/17/13 — JE selected carpet 1 selection on back order
8/19/13 — 3 B's to meet with JE to review Project
9/3/13 — 3 B's on site to Water Test MBR Terrace
9/17/13 — Carpet on site, will be installed prior to next visit
unless
given other direction
9/18/13 — Forwarded E Mail to JE & RK showing gutter
issue
9/24/13 — 3 B's on site, sealed existing gutter cap & water
tested
leaders.
9/27/13 — Forwarded E Mail to JE & RK noting prexis
ting issue,
seperate to the leak on the Princess Deck ceiling
PVC elbow connected to gutter spout, therefore backup water
causing overflow In metal moulding & fasia of terrace
Leaders sealed correctly, terrace & gutter flooded with water
-
no leaking from ceiling
Water sprayed on wall below windows — leakirig occurred,
3 B's
temporarily sealed area.
3 B's recommend cutting section of stucco & flash area correc
tly
attached photos
10/4/13 — 3 B's Proposal to be forwarded
Page 8
EFTA01124742
Zorro Development Corp - Project Report_10/
29 - REPAIR T START END mgsr.cosT
04/13
NOTES
MUSES P119.14 STATUS
5/9/13 —Vendor on site
5/18/13 — Bid breakdown forwarded to RK
8/10/13 —JE requested that work be started in Sept 2013
8/20/13 — JE requested that 3 B's submit a bid for Projec
t
9/3/13 — 3 B's on site to review Project
9/24/13 — 3 B's declined moving forward with Project
9/24/13 —JE approved moving forward with replastering
of Pool
&Cleaning Spa tile
9/27/13 — Forwarded Proposal to RK from Lee Sure Pools
Awaiting Direction
10/4/13 — RK will be contacting Lee Sure Pools in refere
nce to
their proposal
11/4/13 — Lee Sure Pools, due on site to start Project
Page 9
EFTA01124743
Zorro Development Corp - Project Report 10/
30 - FRONT GATE START END
04/13
EST.COST NOTES
OPENERS PHOTO STATUS '
Call Boxes/Loops 1_
07/25/13 $10,125.00 4/20/13 —Bid received, requested vendor to make adjustments
+ tax Awaiting
5/9/13 — Received Revised bid. Options & Equipment review
ed Delivery of
5/12/13 — Options & Equipment selected
Gate Loops
5/21/13 — Final bid faxed, unreadable, vendor will resend
to 3 B's
6/8/13 — Final bid from RMC Electric - $11,941.00
6111/13 — RK requested material breakdown
6/14/13 — Material breakdown forwarded to RK
6/19/13 — RMC Electric resubmitted revised pricing to RK
6/28/13 — RK requested that 3 B's submit an estimate.
Have
contacted 3 B's, they will be on site next week to review
7/9/13 — RK neogiated 3 B's bid
NikiRS
, LEIS 7/11/13 — 3 B's Bid Approved.
7/12/13 — Forwarded Deposit Request $6,750.00 to BK &
RK
7/25/13 — Project Started
7/27/13 — Gate 1Controllers & Key Pad installed. New Key
Pad
for Gate 2 faulty, vendor has reordered — attached photos
8/10/13 — Waiting_for installation of loops & Gate 2 Key Pad
8/19/13 — Vendor to meet JE
8/21/13 — Gate 2 Key Pad installed, gate phone lines down,
hence no remote control to operate gates
8/30/13 — Contacted RMC regarding phones & gate contro
llers
will be on site next week
9/2/13 —As of date Gate Loops Not Installed
19/3/13 — 3 B's on site to review Project
9/16/13 — The bid that 3 B's neogiated with RK did not includ
e the
purchase or installation of gate loops, which was on the orgina
l
bid submitted by RMC Electric & E Mail submitted to 3 B's
Change Order by BG
$435.00 9/17/13 — Change Order submitted from 3 B's
+ shipping 9/18/13 — Submitted Change Order to JE & RK
ADOIDVal JE $60.00 '9/18/13 — JE Approved Chang! Order
9/21/13 — Awaiting delivery of Gate Loops to Vendor
10/2/13 — Gate Loops on Back Order, awaiting delivery to
Vendor
Page 10
EFTA01124744
Zorro Development Corp - Project Report 10/04/
31 - PHONES MAIN START END
13
HOUSE
EST.COST NOTES I PHOTO I STATUS
07/17/13 4/27/13 — JE approved installation of new phones at MH
Vendor
Awaiting for Service Provision & Estimated Cost of Delivery of
On Site
Services from Proj 21— Microwave & IT before moving forward
10/07/13
6/22/13 —Awaiting response from Southwestern Wireless on
FCC License Application & Router at MH
7/17/13 — Project Started
7/25/13 - Switch & 16 Phones Installed, awaiting delive
ry date
remainder of phones — attached photos
9/6/13 — Phones due to be deliveried to Vendor
9/15/13 — Delivery of phones to vendor have been delayed
9/30/13 — Phones due to be deliveried to Vendor
10/2/13 — Vendor on site to start installing/punching down phone
s
11/3/13 — Vendor had an emergency, will be on site 10/7/1
3 to
complete install
32— PHONES RANCH START END EST.COST
CENTRAL MILS PHOTO STATUS
6/21/13 - Will forward proposal for Phone System by 6/28/1
3 Protect
6/27/13 - Project On Hold until Microwave Solution resolved
On Hold
Page 11
EFTA01124745
Zorro Development Corp - Project Report 10/
33 - POOL PAC START END
04/13
EST.COST NOTES
Engineering Inspection PHOTO NAM
4/29/13 — Quote forwarded to RK, who requested more detail
$9,100.00 Awaiting
5/8/13 — Revised quote forwarded to RK, awaiting direction
Unit Cost site visit
5/22/13 — Beaudin Ganze on site to review Project
$43,170.00 by Trane
5/29/13 — Beaudin Ganze report forwarded to JE & RK
Approval JE 1 5/29/13 —JE Approved invesigation via camera
6/3/13 —JBH forwarded estimate
A oval JE 6/4/13 — JE Approved moving ahead
Camera Duct Inspection 6/11/13 — JBH due on site
$1,214.91 6/12/13 — JBH on site, complete camera inspection, awaiti
ng
Report/Disc
6/21/13 — Report/Disc forwarded to Beaudin Ganze
7/8/13 — Report/Disc due on site
7/9/13 — Informed that Report has been delayed
RK forwarded Report to JE
7/20/13 — Beaudin Ganze on site to review Project with JE
JE did not approve any design solutions by Beaudin Ganze
8/22/13 — Contacted Dessert Air & fonvrded info regarding
existing space & equipment design
9/18/13 — Site visit expected by Dessert Air to confirm
their
proposed solution
9/19/13 — Dessert Air have rescheduled for 9/27/13
ADoroval JE 9/24/13 — JE approved investigating purchase of new Pool
Pac
9/25/13 — Dessert Air pending visit — placed on hold
9/30/13 —Trane Pool Pac Rep on site
10/1/13 — Trane forwarded all info to Pool Pac
10/2/13 — Forwarded Mech Drawings of area to Irene
1 10/8/13 — Trane due to be on site to confirm air flow details
Page 12
EFTA01124746
_ _ __ _ Zorro Development Corp - Project Report 10/04/13
34- REPAIR & PAINT I START END EST.COST
WORK - ION NOTES pHOTO STATUS
5/7/13 - E Mailed Photos to JE showing work required
Awaiting
5/23/13 - Forwarded all work details to Ion, Including work that
will be required after MBR Terrace is corn leted Direction
6/29/13 - Additional work - Sign on Ado Office Wall
6/30/13 — As of date Awaiting Direction
37 — WELL K START rim I EST
,Plugging 1" Hole NOThi PHOTO STATUS
$15,000.00 jEstimate to Plug 1 st Hole
lie- - START END E$T.COST
REFURBISHMENT NOTES PHOTO STATUS
ROADS CULVERTS
7/27/13 Wdl review with JE on site, of all Roads &Culverts
8/5/13 — Road Base 23 tons $360, Culvert 4ft x 24ft - $1,38
1.85
Culvert 5ft x 24ft - $1,727.24
9/27/13 — Due to high water flow/rain, culvert gone from under
,
road, no access to North Gate Road, past the Caboose
attached photos
9/30/13 — Work begins to return culvert to correct position,
pack
with gravel & dirt, reconstruct road
10/1/13 — Culvert back in place, road passable — attached photo
s
40 — LANDSCAPING $TART Eyp fST.COST
LOG & LODGE NOTES pHOW STATUS
Removal of Dead Trees, Cover Rocks with Soil
Page 13
EFTA01124747
Zorro Development Corp - Project Report
14 - - START END
10/04/13
EST,COST I NOTES
REFURBISHMENT PHOTO STATUS
HOME THEATER
8/13/13 — JE requested replacement of exisiting Sony
Projector
8/15/13 — 3 Vendors on site — Proposals due next week
8/22/13 — JE forwarded 2 Proposals Direction
5/13 — Received 3' Proposal on E Mall
JE requested Purchase of Projector to be placed On Hold dated
as 10/03113
new projector to be released Dec 2013
Acoroval JE $83.08 9/17/13 — JE approved purchase of HDMI Cable
$320.00 + tax 9/17/13 — JE approved 3 B's installation of HDMI
Cable
9/18/13 — HDMI Cable ordered
9/28/13 — HDMI Cable on site
9/30/13 — HDMI Cable installation begins
912/13 — HDMI Cable installed
10/3/13 — New Model of Sony Projector will start to be
shipped
end of Oct. forwarded E Mat to JE & RK with details, awaiti
ng
direction
lg.= START END EST.COST
REFURBISHMENT BOTES PHOTO STATUS
HOUSE EXTERIOR—
LY
09/24/13 $10,100 + tax 8,22/13 — JE Approved Project
3 El's to complete MH. ZDC to complete Garage (Proje
ct 42A)
9/3/13 — Requested RK & BK for Deposit of $7,500.00
Deposit received by 3 B's
9/24/13 — Project Started
9/27/13 — Work continues — attached photos
10/2/13 — Stucco complete, vendor working on color sampl
e
10/4/13 — Work continues attached photos
JJ has recommended that we use a synthetic stucco, forwar
ded
this Information to JE. Extra expense of $2,000
Page 14
EFTA01124748
Zorro Development Corp - Project Report
42 A 7 - -
10/04/13
T END EST.C--OST NOTES
'REFURBISHMENT PHOTO STATUS
'GARAGE EXTERIOR -
LV
09/30/13 1 $1,543.26 ,e1/30/13 — Project Started
10/2/13 — All garage walls have been primed
10/3/13 — Priming of all trim on Garage & House started
attached photos
43 - REFURBISHMENT $TART END EST.COST
LANDSCAPING - LV NOTES PHOTO STATUS
8/22/13 - JE Approved Project
Cover Rock with soil, Pinion Installation Awaiting
8122/13 - Forwarded JE suggested colourful plant material Direction
for discussed areas — awaiting direction on E Mall
9/16/13 — Router Tilling Complete. Ready for Top Soil dated
9/18/13 — Forwarded JE & RK breakdown of installation/purchas 10102/13
e
etc of sod. Total $5,512.50
9/18/13 — JE asked how much sod. 5,350 snit
9/27/13 — Reviewing sod estimates
10/2/13 — Resubmitted revised installation/purchase etc of
sod
to RK. Total $5,356.25
tlalraligICE START gp EST.COST NOTES PHOTO STATUS
9/27/13 — Forwarded JE & RK estimate to repair Lodge
Roof
attached estimate & photos
9/27/13 —JE Did Not Approve Project
Page 15
EFTA01124749
Zorro Development Corp- Project Report 10/
45 - NORTH GATE START
04/13
PEKE REPAIR
SI EST.00ST NOTES PHOTO STATUS
09/30/13 10/04/13 $1,014.94 9/27/13 — Due to high water flow/rain, North Gate Fence line
as X Complete
been washed out — approx 150 ft needs to be replaced/rep
aired
attached photos
9/30/13 — Material Purchased. Machinery relocated to
area
complete
10/1/13 — Work started, removal of broken fence comp
lete
10/2/13 — New
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- e065fa2d-765d-490b-a799-ae61e94c6743
- Storage Key
- dataset_9/EFTA01124735.pdf
- Content Hash
- 72f2d3bcabe98a9037f7a3e7c788cb70
- Created
- Feb 3, 2026