To: Brice gorcion
From: Jeffrey Epstein
Sent Tue 1/10/2012 8:11:38 PM
Subject: Re: VI Gunite
begin work 15th feb
On Tue, Jan 10, 2012 at 5:02 PM, brim gordon e > wrote:
FYI
Tom, Darren and I spoke with Rcx this morning
Continent on blue plaster availability for flag pool, which will be confirmed 2 pm today AST
recommend this basic schedule
starting this week
green light material order/empty pool- 3 wks for tile main compound pool delivery, 2 weeks blue
plaster flag pool
heater relocation and start flag pool refurbishment
replaster flag pool/ fill
main compound material arrives/empty main compound pool
tile main compound pool/ fill
7 - 8 week duration total for both pools
work schedule, if required 7 days a week with option to start early and finish later than -fpm
payment schedule will be confirmed once availability ofplaster is confirmed today
are you ok with this
please advise
Brice Gordon
Little Saint James
USVI
Phone:
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
EFTA_R1_00232560
EFTA01844182
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any pan thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation@gmail,com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA_R1_00232561
EFTA01844183
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 7450725d-7b5b-42a6-afa0-8f357107806c
- Storage Key
- dataset_10/c7f7/EFTA01844182.pdf
- Content Hash
- c7f79bb35f0e842f5f948e918288ffa3
- Created
- Feb 4, 2026