Punch List — per JE directives and Updates as of March 30. 2012
1. Bug —with proper rug pad for JE bath and original 3 guest room rugs - delivered to Tropical in NJ 3/23, sailing
4/4, EDA STT 4/7
2. Flagpole Bath and Cabana — slipcovers for sofa/cushion on site, piping around arm chairs requested — extra
fabric on LSJ 3/27
3. Five Palms
— Interior stucco — ongoing — require filler section at cabinets
- Electrical -ongoing
- Solar - estimate 3/9
- Floor — material ordered 3/23
- Doors location and fabrication — manufacturer has submitted a quote and shop drawings 3/23
- Lighting schedule
- Concrete top section completed
- Coral stone bull nosing ongoing - modeled after MC — in progress
- Big Slab installation completed (require 4 holes for trees — size required — completed)
- Fire pit work on hold until JE arrives
4. Grotto — steps demolished, starting hammer work and excavation, debris placed at dump site
— Concrete steps ongoing
- Determine shelter height — roof for Grotto shed
- Columns to be laid out by JE
5. Heli Garage — completed
6. Heli Road — saw cutting completed — wall extension in progress — 4/3
7. Hangar —floor sanding in progress — 40'X50' area for slab, 3 foot wall around it — containment for ISO
Fuel tank — bathroom and room divider —subcontractor for painting require,g
8. Steel Shed - have estimate for building, schedule to be forwarded 3/10
9. Triangle — needs more dirt — additional dirt added
10. Entry Tree Lights - confirmed ground lighting
11. Library Dehumidification — commences week of 12 Mar
12. Solutions for Generators -drawings complete for bid package
- generator room sound proofing, need to confirm schedule
13. Top of hill - CLEAN UP - remove rocks and hydroseed - hydro seeding 3/23
14. Tree Order - x 7 - 12ft and 3 — 15 ft Palms ordered per JE directive 3/23 — sailing 3/30, EDA 3/31
- X 2 15ft Palms to be placed at entrance area
15.11k! - Shields — check with Sarah for date, still pending
- Dock box in production
16. Sunken garden berm - continues — hydro seeded 3/23 — moving equipment to start layout
17. Concrete roads at flagpole — per JE build another ramp - completed
18. Bench placements — continues
19. Engineering clean up - continues
20. New vehicles — two more Polaris bikes (800's) — Larry/Brice
21. Dock decking — discuss pressure treated timber/carpeting
- investigate having movable sections
22. Aquarium photos Library — installed
23. Mars Cottage Roof work remains — completion 3/29
24. Mooring Permit — proceeding with bids to place anchors
25. Electrical quotes — forwarded to JE
- Glidden measured on 3/28 - should have price by next week
26. Rationalize Telephone system — Extension list completed, Voice mail set up at
Beach Office, Kitchen MC, Managers Cottage
EFTA01107323
27. Gates - to hide engineering both at top and bottom of hill
Bill reviewing light weight gates for bottom of hill — JE advises three 8 foot gates - bi-fold design running in
track on the ground - reauire design— contractor on site - measured on 3/30
28. Engineering service road reshaped - continues
29. Dock lighting - barn lights installation completed
30. Guest House at Beach 3 — sited
31. Chillax room — furniture piece required for electrical/media equipment
32. Replacement Transformer Mechanical building — have bid — reviewing shipping — Brice to finalize cost
comparisons — refurbishment versus new
33. Photos for Chillax bath — installed
34. floating Dock — substructure support in place and bolted (covered with wood)
- JE design to handle 2 jet skis
35. Midnight Express —trailer on site, Midnight Express resting in it
36. sundial - completed, awaiting further JE directive
37. Boats — Midnight —sell existing motors —ad placed in both Daily News (3/24-3/31) and Island Trader (3/29)
Purchase x 3 Yamaha 300 motors
- PRD — sell
- Calypso - refurbish
38. Sod — quoted with Deal Time (Adelbert Ledee) — on hold per JE
39. Motor court wall extension — completed
40. Hydro seeding— as much as possible especially when it rains
41. Bamboo - order bamboo in Puerto Rico - to put bamboo at least in the sunken garden berm as well as
other areas
EFTA01107324
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 4e37446d-6c1b-49cb-a3b5-984c828b9760
- Storage Key
- dataset_9/EFTA01107323.pdf
- Content Hash
- 1f50bf8fb0d961ee7e053e1431205996
- Created
- Feb 3, 2026