Punch List —June 5, 2012
1. Five Palms — TOP PRIORITY
- Laying conduit and pulling cable — continues
- Exterior Door Shutters — PO rejected by JE, on hold awaiting design
- Painting — inside completed 5/30
Outside to be completed after visit
- Furniture — Sofa — leather samples JE will review while on site
- Desk, Rug, Lamps installed
- Lights— Parrots finished, awaiting approval on down lights
- Mirrored siding — Panels ordered — EDA to Tropical FL 6/7 — scheduled to sail 6/8, EDA on STT 6/12
Glue on site
- Tapestry Molding for Ceiling - bid rejected, need to review design with JE
- Transformer building - Building 5/31, 5/25 - final electrical hookup 6/8 — temporarily powered by generator
- Flooring — installed
; Jaw pit —gas and grate coming down on plane
- Books — books on site will relocate over the week of 6/4
- Benches —two benches out back
- Road grading
2. Grotto -
- Floor resin
- Genset wiring — scheduling to be determined
3. Berm/Top of Hill
- dirt and rock needs on top of hill needs to go ASAP
- hydroseed top of hill
— 4 large planter boxes with small planter inside require construction — size to be determined by JE
- cleanup and excavate — continues
- remove rock screener - completed
4. Engineering/Maintenance Yard
- Steel Shed — foundation in progress
- Metal Sheets on old building will be replaced week of 6/4
5. Triangle — landscaping direction required from JE
6. Flagpole Pool Cabana -
- Recovering of sofa/chairs — completed, need to review piping with JE while on site
- Furniture - review another piece of furniture — Sarah
7. Entry Tree Lights — installation complete
8. Solutions for Generators — Sound proofing solution forwarded to JE, require direction , wall built
9. Tiki - shields with the vendor in Wewak (5/4) — working on the permit to export — will take 1 to 2 weeks
10. Dock —
- Decking — replace all damaged boards and carpet complete
- Floating Dock —
-Jet ski Docking - review
- Table/Dock Box — Bill starting 6/4
11. Kite House — review of wooden outside furniture - Sarah
12. Chillax Room — requires furniture piece for electrical/media equipment — Sarah
13. Chilax Bathroom - requires blue rugs for bathroom & vanity area — Sarah
14. Mechanical Building
- Replacement Transformer — approved to purchase — ordered
15. Boats
- Midnight Express — purchase Yamaha 300 motors, install by Offshore Marine
- PRD — sell
EFTA01147442
- Lady G — sell
- Big N - sell
- Calypso — refurbish
16. Gym Road - road grading after Five Palms — continues
17. Outside Master Bedroom — lock installation 6/2
18. Timers— review installing timers on air conditioners, irrigation water systems, and lights
19. Life vests — new life vests, yellow and black, in men's and women's sizes — at least 2 of each, if not 4 in
unisex size so they can be exchanged - Sarah
20. Beach lighting — per JE, replace existing transformers for the beach lighting of palms around the salt pond
and beach
21. Pergolas— construct 3 pergolas for benches at the top of the hill —continues
22. Main entrance/gravel/grade - complete
23. Red Hook Dock — grey carpet and seal Nanna
24. Wind Door —wind door on kitchen side needs adjusting
25. Landscaping— gardenias
26. Solar lights
27. Roads— grade all roads — Wednesday 6/6 — Tom - please review all roads so you can pitch, drain, with Jules
and Craig
28. Library — lights on bookshelves need attention
- temperature?
29. Main hill — asphalt path
EFTA01147443
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 4550f75c-77c6-4889-97f8-42b19b3ed84d
- Storage Key
- dataset_9/EFTA01147442.pdf
- Content Hash
- 1b2a14fa36dc9784e1b7d17b3ad5be66
- Created
- Feb 3, 2026