03/11 - 03/25 2019
Please note:
This is a summary of the last week's focus, not a comprehension of all projects.
Carpentry. JE approved lattice paneling from carpenter samples. Now building to
spec for tiki kitchen. Removed all rusty hinges from MC interior kitchen shutters and
replaced after treated and painted as replacements could not be found locally.
Opened cistern hatch. Assisted with putting master back together after floors. Built
secure tool storage cabinet for wood shop. Replaced FPP latches on both gates.
Electrical/Plumbing. Completed install of both dishwashers. Timers here installed.
Ordering more. All lighting in LSJ installed. Bulbs ordered. Replaced all recess
ceiling lights around MC veranda. Completed the electrical and plumbing and gas tie
at LSJ tiki kitchen.
Engineering. Swap out bucket for hammer and then back on big excavator.
Received new cement mixer and commissioned it for use. Finished commissioning
the John Deer. Waiting for hitch that will hopefully arrive this week. Rust remediation
on light towers. Cleaned equipment and buggies. Buggy repairs and maintenance.
Parts arrived for bikes, so working on those now.
Heavy Equipment. Dug deep corner footing for MC flowerbed. Did seawater intake
well at GSJ. Completed site work for container structure at Christmas Cove. Cleaned
seaweed off beach at GSJ (ongoing battle with seaweed has begun). Graded all
roads on LSJ and cleaned beaches. Assist with moving BOLs. Completed septic
install on GSJ for main compound.
Housekeeping. Put master and kitchen back together. Usual rounds.
Landscaping/Masonry. Assisted with completion of install of GSJ main compound
septic. Began pebble beach stonework. Received large order from ABC. Will be
working those in coming week. Boschulte was here Saturday 3/23 spraying.
Marine. Little C is back and in operation. Barge also back in operation, but
scheduled for more work in PR, April 22. Rich needs to approve propeller purchase
so can be installed before Boscoe heads over. Randy is back. Patrick's foot is
fractured. Nanna and Zodiac were hauled out and cleaned. Dock maintenance
(cleats and lines).
Painters. Treated and painted interior hinges on MC kitchen shutters. Treated and
painted exterior hardware on master. Work in progress around entire main
compound.
RO/Maintenance. Assessed master cistern. Currently working with contractor for
cleaning & sealing master first, then all remaining cisterns. Developing maintenance
and record program for all cisterns. Water pump at FPP Cabana needs replaced.
Contractors on island:
Absolute Flooring — Leaving master floor scratch for now, so no further work needed
in bedroom. Cabana 1, 2, 4 receiving final coats today. Cabana 3 needs light
EFTA01223575
sanding and touch up. FPP cabana — addressing edging on floor outlets and edging
in all cabanas. I asked Luis via email to instruct the guys to wax library. When I
asked them for a schedule this weekend they said Luis had not spoken to them
about it. I will call him again. Perhaps would be helpful for Rich to give him a call as
well.
Peter Elie - Forms at Pebble Beach have been stripped. Dupson has begun
stonework. Peter formed footing and poured concrete for deep end of flowerbed
planter. Started forming and reconfiguring the door for the bunker below 5 Palms.
Jeffers — On hold pending delivery date for concrete coloring.
Reefco — Working on bid for variable speed air handler replacement and install of
new units in master bath and bedroom. We have one in possession. Second one
being purchased by Rich. Confirmed access to attic to get them up.
Danny — Continuing work on MC Flower Bed.
Countertops for LSJ cabanas 1-4 & FPP Kitchen — Material order placed and install
set for first week of May, pending wire transfer. Rich, please confirm. If selection of
countertop for tiki decided by 3/29, can also be installed at same time.
Other Notes:
Rust remediation. Maurice Bedminster has been hired for rust remediation and
other maintenance and improvement work. He is installing the additional tiki kitchen
tile requested by principal this week. Will begin rust remediation work behind Host-U
who will be cleaning underground spaces, project led by Cashkim to begin Tuesday
3/26.
Master cistern. Contractor bidding work 3/25. To begin as soon as possible
emptying, cleaning, and sealing the master cistern. Will also provide bids for all
cisterns on LSJ and GSJ.
Library filter (re: Cashkim Photo). This is the seawater intake filter for the two
chillers that are part of the library a/c system. It filters the seawater for the heat
exchange that allows for cooling in the library a/c system. All that does is circulate
around the compressors and pulls away any heat. In other words, that is seawater
coming in, spinning in one circle on the outside of the running unit (does not touch air
flow), and going right back out. We have currently on order and are expecting within
the next two weeks, a stainless steel, three-times-larger-capacity filter cartridge that
will replace that unit. As it stands now, that unit is cleaned twice a week and because
it is plastic, we can't use any strong cleaning agents that will kill the algae that comes
in from the sea. We will be able to do this with the new stainless steel unit. But to be
clear, the seawater does not go any further than that shed and has nothing to do with
air flow.
5 Palms Power — Bid awarded to Frank's Electric. Awaiting material delivery
schedule. Scheduled to begin excavation of trenches first week of April.
EFTA01223576
On 3/26 all trash bins on LSJ will be emptied. Same to follow on GSJ on 3/27.
Containers to be moved from LSJ to GSJ this coming week.
Mike will send separate report:
Boschulte on permitting
Quotes on at least two options for fuel truck refit and researching flatbed for existing
truck chassis
Steel buildings — working with Bryan Buck on building replacement
EFTA01223577
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 41089295-75d1-4d1b-b5da-6555e3209141
- Storage Key
- dataset_9/EFTA01223575.pdf
- Content Hash
- c70520a7c26353e8dc2523cefaaa5565
- Created
- Feb 3, 2026