Brice,
Here is a price to remove the limestone and concrete for the terraces. Balistre removed
and reinstalled.
Remove existing limestone from deck(s).
Remove concrete by sawcutting and light chipping as to not damage the deck or
membrane further.
I will use a lift to get the pieces down from the terraces safely and efficiently which will
be by hand. I will use material lifts to remove the banisters safely. The sections will be
cut along each joint and removed. Dispose of demolition materials on the property.
Clean area
Materials 0.00
Lifts 2000.00
Labor
Supervision 2800.00
Demo 6 guys 12 days 15,000.00
Cleanup 2 guys 2 days 350.00
Work comp $ 3600.00
Plus markup
$ 28,850.00 plus tax
This work is labor intensive because of the limited access to the work area, and the nature
of the project.
There is a thermoplastic membrane under the concrete, and we can install a new one on
top and mechanically fasten or fully adhered (glue down the new membrane). The cost
of a new liner is about 6.00 a sq. foot installed or about
$ 12,000.00
New deck on east terrace.
Material
35 sheets treated 4x8 3/4 plywood
43 2x12x16 treated
25 2x12x12 treated
27 2x4x16 treated
EFTA01146360
9 2x4x12 treated
Miscellaneous materials (nails, glue, deck screws, etc...) $8,500.00
Install liner on top of new deck.
Deck to have minimal slope of approximately 1/8" sloping east
Labor
Supervision 1800.00
Mobilization and prep 2 day 700.00
Installation of new deck 5 guys 6 days $7,200.00
Cleanup 2 guys 2 days 350.00
Travel for entire Job 20 days (per diem, gas) 4,200.00
Work comp 2500.00
Plus markup 4700.00
$ 20,400.00 plus tax
Project will take approximately 20 days to complete.
Additional cost for unforseen circumstances, once the linestone and cement are removed.
No electrical, plumbing or HVAC in quote
Total for job is $69,750.00 plus tax includes roofing membrane and deck, materials and
labor.
Does not include modifications or alterations to the gutter system.
We can start Monday September 24th
Please call me if you have any questions at 450-3654.
Thank you,
JJ Blea
EFTA01146361
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 3e8cc821-bfd3-4626-9917-37d0bcd4bbe5
- Storage Key
- dataset_9/EFTA01146360.pdf
- Content Hash
- 64f1ec73614def13e43a20b049f11746
- Created
- Feb 3, 2026