JE Punch List —July 11, 2012 Directives
1. Clean Up
- Top Desal Plant
- Engineering
- make as many barge runs as necessary
2. Equipment and Vehicles
- Sell equipment — updated list forwarded 7/10
- Buy new Kawasaki bikes and mules — estimated costs forwarded 7/11
3. Computers
- Buy new computers — 2 Macs Desktops & 1 Laptop — Captains Office
4. Five Palms
Internet/Phone will be up once switch is installed. Francis to bring 7/14, along with 2 routers
- Phone set up left of desk — ready for switch
- Wireless inside only — as of date 7/10 via JE
- Computer — as of date 7/10 not required via JE
- Shield Chains - COMPLETE
- Exterior Door Shutters — storm panels for windows - COMPLETE
- estimate for double door due 7/13
- Painting - outside to be completed via JE direction
- inside to be completed via JE direction
- Furniture — outside furniture ordered — due to ship to Tropical 7/12
- Piano Bench — ordered 7/10 — Sarah
- Picture Frame — measurements forwarded to Sarah
- Mirrored siding — liquid nails — will cover entire panel with glue when the next one falls off
- Tapestry Molding for Ceiling — Ion
- Transformer Protection Wall — on hold until manpower available
- Fire pit — work continues, completion expected AM 7/12
- Cabinet Latches - COMPLETE
5. Grotto
- Floor resin white — completed by 7/13
- Genset wiring — wiring complete Danny reviewing auto start from Kite House
6. Berm/Top of Hill
- Paint Pergola — COMPLETE
- Electrical — Low voltage transformer in place, placement & connection of lights completed ASAP
7. Engineering/Maintenance Yard
- Steel Shed Concrete Pad — COMPLETE
- Metal Sheets - on old building will be replaced ASAP
- Engineering Storage & Shelving — work to start when carpenters available
8. Triangle -
- Landscaping direction required from JE
9. Flagpole Pool Cabana -
- Furniture — Investigate new desk, new furniture more like Pool Cabana PBI
- Relocation of orange sofa to Media Room
10. Floating Dock
- Jetski Bumpers — Ordered - ETA 7/24
- Table/Dock Box — Sample handles complete, JE requested larger, will forward new samples by 7/13
-Swim Ladder —
- Diving board Option — will forward by 7/13
- Wooden Bumpers — to cover concrete stripping — start 7/12
- Painting — Railing, Cross Brackets & Robe Hooks - COMPLETE
EFTA01107280
11. Entry Tree Lights
— Lights on site, electrical installed ASAP
12. Solutions for Generators
— Soundproofing Installation — to be completed 7/13
13. Tiki
— Shields
14. Kite House
— relocation of outside furniture from 5 Palms once new 5 Palms furniture on site
15. Chillax Room
— requires furniture piece for electrical/media equipment — Sarah
- JE to review placement of desk from Pool Cabana
16. Chillax Bathroom
— storm panels for windows - COMPLETE
- require blue rugs for bathroom & vanity area — Sarah
17. Mechanical Building
- Replacement Transformer — estimated date to be shipped from factory (Illinois) 8/21
18. Boats
- Lady G — sell - will be placed in hurricane storage 7/19
- Lady K — sell — survey forwarded to Darren & Rich, suggested price $225,000
- Big N - sell
19. Timers
— review installing timers on air conditioners, irrigation water systems, and lights
20. Beach lighting
— per JE, replace existing transformers for the beach lighting of palms around the salt pond and beach
21. Transient Surge Protection — will review and forward estimate ASAP
22. Wind Door — wind door on kitchen side needs openers/wind door stops — COMPLETE
23. Landscaping —Josephine to visit and organize garden
24. Solar lights — Ordered, placed every 30 feet
25. Roads — grade - Jules work continues
26. Library
- Lights on bookshelves need attention — will complete ASAP
- Temperature - STABLE
27. Main hill
— Asphalt path — top and bottom to be completed by JE's direction. Will start 7/19
28. Master Suite
- Large master bed planting - COMPLETE
- Put self-closing hinges on the master bedroom door to the outside, completed by PM 7/11
29. New Employee Bathrooms
30. Gym
- New punching bag — ordered due 71,, 7/16
- Wiring — tidy up due to be completed 17 — Francis bringing balance cables
31. Benches
32. Danny Vicars — schedule boat driving lessons
33. Main Compound — JE needs to confirm that the wireless coverage over the main pool area is adequate
34. Marine/Woodshop Work Area - phone required
35. Beach Office
- complete electrical overall required
- waterproofing/sealing/painting required
36. LSJ Mooring — requested a copy of approved permit - Darren
36. Hangar
EFTA01107281
- Jermaine to redo Internet at hangar
- Fuel Containment Pad — draft approved with drainage incorporated, waiting for updated plan
EFTA01107282
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 3d1362d8-4f53-4419-84f8-b68fcff87856
- Storage Key
- dataset_9/EFTA01107280.pdf
- Content Hash
- 3ed1eee21d55b838287ec6dc163169ee
- Created
- Feb 3, 2026