SIEMENS Siemens lndustry,Ini:
■
SCU & DPU
FAST FORWARD MIGRATION
PROPOSAL
PRESENTED TO:
9 East 71" New York, New York
PRESENTED BY:
Bradley Rickert
Siemens Industry, Inc.
1101051
Rev 0
January 28, 2011
EFTA00608580
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
Table of Contents
L Summary 2
I
I. Project Description 5
A. Project Schedule 5
B. Project Coordination Meetings 5
C. Project Management Functions 7
1. Minimum Occupant Disruption 7
2. Smooth Transition to new System 7
3. Total Quality 7
D. Project Team 7
E. Total Quality 7
//. Proposal 8
V. Appendix A, System Specification Data Sheets
1
EFTA00608581
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
Summary
Siemens Industry is pleased to present this proposal for the upgrade of the environmental monitoring and
control system at 9 East 71".
This document contains technical information about the scope of the project and the methods to
accomplish the project with minimum disruptions to the facility. The information contained in the
appendices describes the equipment furnished as part of this proposal.
This proposal offers a solution to increase processing performance, 18 x greater memory capacity (up to
72 MB) and increase system performance Up to 100 x faster communications.
Current Situation
The existing building system was designed and installed by Landis & Gyr with is now Siemens Industry.
The Building Automation System currently is controls the building Air handlers and chillers systems at 9
East 71st. These systems are using technologies from the early 80s and have passed there life span.
Current Issues
Thirty years is an eternity in the semiconductor industry. Third-party components essential to the
Standalone Controller Unit (SCU) are simply no longer being made. True to our commitment, we have
ensured a supply of repair and replacement parts to facilitate the servicing of SCUs as long as possible.
Still, now is the time to fast-forward your building automation system into the future.
Proposed Solution
We propose to upgrade 6 existing controls (SCU) and 3 Digital Point Units (DPU) systems with a state-
of-the-art PXC Controllers.
The Standalone Control Units (SCU) at 9 East 71g were introduced in 1983. Yet every SCU that has been
installed since then has proven that Siemens commitment to compatibility. Major technological
advantages in our building automation system have continued to be supported the always reliable
controllers.
But 30 years is an internally in the semiconductor industry. Third-party components essential to the SCU
& DPU are simply no longer being made. True to our commitment, we have ensured a supply of repair
and replacement parts to facilitate the servicing these controllers as long as possible. Still, now is the time
to fast-forward your building automation system into the future.
Investment Protection — System 600 Apogee® is built on a twenty-one years history of backward and
forward capability for the entire family of System 600 products. This ensures that as future technological
advances become available 9 East 71" and now will be able to integrate them into their existing system.
Additionally, its open system architecture allows for integration to over three hundred other systems.
Power Open Processor has the following enhancements,
2
EFTA00608582
9 East 7
Technology Upgrade of the
Environmental Control System
1/28/2011
• More memory from 4MB (SCU) to total of 72MB,
• Faster processing from 16MHz (SCU) to Power PC running 48MHz,
• An option for direct connection to an Ethernet TCP/IP Building Level Network (EBLN),
• Space for a compact flash card for future use.
• Adaptive Control (see attached data sheet)
llll
•••1“;;Ji44i11144,44‘.:::Ii ;L:.• :41
• I(( t I: •
ip:•••••• • w• • •••fl i i n .•••••,. it•;•••••,,,n
111111141. 1 11 llllllll IIII1 lllllllllll 1 ".
•••••••••• ••••••••• •••••••••• llllll ••••
The "Power" Open Processor refers to the latest generation controller platform for use in the industry
leading our new PXC controllers. These controllers are based upon a state-of-the-art design, architect
around the Motorola Power PC microprocessor and offer the latest in performance and extensive memory
capacity. With a faster processor and more memory, it positions 9 East 71u with the ability to take
advantage of future APOGEE features and enhancements as they become available.
WindowVP —111=
PERSONAL COMPUTER OS
-. 4.77 Mh
tt. FASTEST CHIP
1 983 C2003
LARGEST HARD DRIVE
FASTEST MODEM
300 bps ilbps
This upgrade program will allow 9 East 71a to preserve each of the following system assets
No Chages Upgrades
3
EFTA00608583
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
System engineering cost
Electrical installation
Field panel hardware XX X
Sensors and actuators
Field wiring
Programming
Workstation hardware
Graphical interface
Create new point database
Tools to convert database X
System commissioning
Operator training
System startup XX X
Extended system downtime
Facility operation impact
The new Power PC field panels have other advantages as well. When compared to the existing SCU
controller, the new controller power processor has:
APO cir.
♦ 5 x greater processing performance
♦
♦
18 x greater memory capacity (up to 72 MB)
Up to 100 x faster communications via an Ethernet port option
P`cW
. INSIDE
Your initial investment in the Siemens automation system many years ago now
provides a strong foundation for the future.
This upgrade will replace 6 Standalone Control Units (SCU), 3 Digital Point Units (DPU), and upgrade
the systems front end software.
4
EFTA00608584
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
Project Description
A. Project Schedule
The anticipate the project will take approximately two months to complete including
engineering, material delivery, installation, start-up and commissioning.
The project can be broken down into four (4) components as follows:
1. Engineering, Submittals and Material Ordering.
Detailed panel layouts will be provide on AutoCad. These drawings will form the
basis for the final As-Built drawings. All As-Built drawings will be provided to 9
East 71k1 at the completion of the project for record keeping. After the submittals
are approved material will be ordered and delivered to the site.
2. Equipment Installation
The upgrade will be done on AHU by AHU . The base of the system design will
be on RS-485 Network.
➢ SCU will be upgraded to PXC controllers.
Upgrade will be done on straight time.
We will reuse the existing SCU enclosures.
3. Start-up
After the physical installation is complete, each controller will be checked for
proper operations. Controllers will add to the System 600 network for monitoring
and control. At the existing Apogee graphic operator's consoles color graphics.
4. System Testing and Turnover
After each controller is upgraded, the control system will be thoroughly tested.
For each controller for the proper sequence of operation will be verified in the
presence of an authorized 9 East 71k1 representative.
B. Project Coordination Meetings
5
EFTA00608585
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
Siemens Industry will conduct weekly project status meetings with 9East 7l" to en sure
proper coordination and information exchange. Since the installation will be done during
normal hours, access to the equipment / controllers will be scheduled during these
meetings.
Summary;
The above is a brief overview of the network and controller upgrade of the monitoring and
control system proposed. See the equipment data sheets in the Appendix for more information.
Siemens Industry is dedicated to the success of our clients. The successful completion of this
project will extend our business relationship, one that you can continue to depend on well into the
future.
6
EFTA00608586
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
C. Project Management Functions
Siemens Industry professional project management team will ensure the following critical
components:
1. Minimum Occupant Disruption
2. Smooth Transition to new System
3. Total Quality
Through our broad base of industry experience and professional project management
team, Siemens Industry will meet the challenge this type of project presents.
D. Project Team
This project's success not only depends on the Control System but the teamwork and
coordination of the project team. This proposal is based on close cooperation of each
team member from Siemens Industry and the 9 East 7l" facilities staff to ensure an on
ime, high quality system installation. Our team members are:
TITLE ROLE/RESPONSIBILITY
Project Manager • Primary client contact
• Project management
• Quality control
• Subcontract administration
• Commissioning supervision
• Payment Requisitions
• Supervision of subcontractors
• Supervision of systems specialists
Project Engineer • Project documentation for as builts
• Technical coordination with subcontractors
• Graphic creation
• System design and programming
Systems Specialist(s) • System start up, testing and commissioning
• System programming
• System operator training
E. Total Quality
Siemens Industry Total Quality Leadership program is setting the pace in the industry for
Total Quality. This project will provide the opportunity to capitalize on a working
partnership between Siemens Industry, and 9 East 71" staff where close cooperation will
be a critical factor in the success of the project.
7
EFTA00608587
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
Proposal
Siemens Industry will provide and install 6 PXC controllers and TX I/O to the existing RS-485
network. The result of this project will be a state of the art building automation system for the
building, which will provide a comfortable environment that can be centrally monitored and
controlled. See the following page for a detailed Scope of Work. Prices are based on work being
done on straight time. Prices are valid for sixty (60) days.
Investment:
$72,350 (Seventy Two Thousand Three Hundred Fifty Dollars) Plus Tax
El Ming by Siemens Industry, Inc. ❑ Wiring by others ❑ No wiring required
Terms of Payment: n Monthly Progress Payments
• 0 Retainage
• 20 % in Advance
pi Net 30 From Invoice
The Terms and Conditions of Sale shown on reverse are a part hereof
Proposal Accepted: Proposal Submitted:
Siemens Industry, Inc. is authorized to proceed with Siemens Industry, Inc.
the work as proposed.
Purchaser By Bradley Rickert
By Title Account Executive
Title Date January 28, 2011
Date
EFTA00608588
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
Scope of Work
We will provide and install Siemens Industry controllers to replace the 6 existing SCU and 3 DPU on the
existing RS-485 network. The following scope of work is for the upgrade of the complete system. The
equipment detailed below is what is required to complete the upgrade of the building.
We Include:
4. Upgrade of 6 SCU panels with PXC controllers.
4. Upgrade of 3 DPU panels with TX- I/O Modelers.
4. New Dell workstation.
4. Project management for coordination of system installation.
C. All existing parts will be returned to Siemens Industry.
4. All existing sensor, valves and dampers will be reused.
d• Any existing sensor, valves and dampers not operating will be identified and brought to the owners
attention for repair by others.
C. Start-up and system checkout.
C. All Controllers will have Adaptive Controls
C. As-Built drawings.
d• One ( l) Year Warranty
We Do Not Include:
6• Sales Tax
6• Set up of Adaptive Control loops
9
EFTA00608589
9 East 71"
Technology Upgrade of the
Environmental Control System
1/28/2011
Appendix A, System Specification Data Sheets
1. PXC Controllers
2. Adaptive Controls
10
EFTA00608590
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 36838bda-559c-4fd9-99cf-f39da607ed1e
- Storage Key
- dataset_9/EFTA00608580.pdf
- Content Hash
- 538271c40dc012c8264e3b42fe784cf1
- Created
- Feb 3, 2026