ZORRO DEVELOPMENT
1/30/14
Satellite/Internet:
4th Feb - Advanced Communcations due on site to install New Router
30th Jan - Revised Pole & Power Supply estimate forwarded to RK for review/approval
31' Jan — RK & BG will complete final review of ISP (Spacenet) proposal
Pool Replaster/Spa Tiling: - attached photos
Pool plaster is curing.
Pool will be drained Feb 10th for plaster polishing to remove stains & boot marks
Pool expected to be fully operational by lm week of March
Spa Water Line Tile Band removed & replaced with new
Small Spa Tile due on site 3nd Feb.
Spa expected to be fully operational by 5th Feb
Sony: - attached photos
IR installed to coffee table, mouldings & projector cover reinstalled
Tablet updated with Macros.
Need to wait for new update for Sony Tablet, Kitcat to Jelly Bean for Apple TV Remote
Apple TV can be controlled by Apple TV Remote
Picture produced by Blue Ray very grainy, installer requested replacement unit due on
site 31' Jan, Brice will instal
Under present Internet Speeds it will take 70 plus hours to download a 4K movie
Dakota Well:
Big Rig was due 27th Jan, but was held up
31' Jan — Big Rig due on site
EFTA01166948
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 362f128f-b505-43ca-8621-d543c00c4faa
- Storage Key
- dataset_9/EFTA01166948.pdf
- Content Hash
- 408a7ea7d89b1e36b5cf7d8ab77ce5da
- Created
- Feb 3, 2026