From: Richard Kahn
Sent: Saturday, December 22, 2018 1:14 PM
To: Jeffrey Epstein
Subject: Fwd: Status Update for LSJ Pump Station and GSJ Containerized plant
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York NY 10022
=egin forwarded message:
From: <
Date: December 22, 2018=at 8:09:40 AM EST
To: "'brice gordon'"
Cc: "michael lid=en" —R=chard Kahn"'
Subject: Status Update for LSJ Pump Station an= GSJ Containerized plant
Brice:
As of close of business yesterday, here is were everyth=ng stands on the two ongoing projects:
LSJ Pump Station<=b>
1. The basket strainers arrived yesterday, ther= were the last items we were waiting on to finalize the
system fabrication.=o:p>
2. The equipment is scheduled to ship to Tropical on Janua=y 3rd. We will coordinate shipping with
Daphne once we hav= made final arrangements.
3. Assuming the equipment arrive= late the following week, we would propose coming to St. Thomas the
week of=January 14th to install the pump station equipment, install the n=w seal for the cartridge filter housing, replace
the pH probes and associat=d wiring and update the controls for the new configuration. I underst=nd the fiber optic
cable has been shipped from AVL. When do you antic=pate having it installed so we can finalize the new controls? This
wi=l drive the equipment installation schedule.
EFTA_R1_01802526
EFTA02608983
GSJ 25K Plant
1. The container will be completed late=next week and ship to us on January 3rd or 4th. =/o:p>
2. Installation of the equipment will take approximately 3 week= which puts shipment sometime during
the week of January 28th with installa=ion probably the week of 11February.
3. On your end, have=you decided on the routing of the feedwater and brine disposal pipelines?&n=sp;
There will also need to be 208 three phase power at the seawater pumpin= station as well as one control conduit from
the pump station to the RO pla=t. There will also need to be control conduits from the two cisterns t= the RO plant as
well as the interconnecting piping (1.5 to 2" diam=ter is recommended).
=/o:p>
Our facility is closed next week through Ja=uary 2nd. If you need any technical support, I am availabl=. Hope
you and the staff have a great holiday season and I look forwa=d to working with you to complete the water upgrades
on both of your island=.
Dean Bedford PE
Gemin= Seawater Systems LLC
8916 SW 44<=up>th Lane
2
EFTA_R1_01802527
EFTA02608984
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 3201a9ae-bdb8-4a58-a48a-9bd3b646b614
- Storage Key
- dataset_11/EFTA02608983.pdf
- Content Hash
- 975f360eaacc4db224b04cb2b27d900a
- Created
- Feb 3, 2026