SUBJECT: SAINT JAMES -DESIGNATED PUNCH LIST & PROPOSED NEW WORK
Please find below the punch list and documentation provided
1. Punch List Items As per September 8th List, with provided Picture Log
reference and Comments.
2. Outstanding Arrears Past Due to remit prior to travel plans
3. New Work New Color Staining - Phase 1
4. New Work New Color Staining - Phase 2
Items Removed from Punch list as they are New Work
5. New Work Shutters' Marquetry
6. New Work: Escutcheons
7. New Work Perforated Panels at the Tilt Top Desks:
Items Removed from Photo Log as they are not part of Punch List
8. Not in Punch List Columns seams cracks
9. Not in Punch List Carver signature on column
Attachments
10. Punch List September 8th email copy
11. Picture Log October 19, 2010
12. Invoice 1098 Outstanding Arrears Executed work Balance [2009]
13. Invoice 1096 Outstanding Arrears Travel expenses Balance [2009]
14. Estimate 2010 Shutters Marquetry and sketches
15. Estimate 2013 New Color Staining - Phase One: Sample definition
16. Estimate 2014 New Color Staining - Phase Two: Labor
17. Upon request estimate Escutcheons
18. Panels Perforations Picture for approval of technique used
19. Upon request estimate New Perforated Panels Installation
24 EAST 64TH STREET
NEW YORK. NY 10011
212 935 6537 fax MT 9)5 6538
infr@facellipmeling.com ST) - Resolution Agreement - Oct 2010 Page 1 / 22
WWW.FANCELLI-PANTLING.COM
EFTA00721946
PANELING
1 PUNCH LIST ITEMS AS PER SEPTEMBER 8TH LIST, WITH PROVIDED PICTURE LOG REFERENCE AND COMMENTS
ITEM # ITEM DESCRIPTION - SEPT 08 PUNCH LIST ITEM STATUS COMMENTS
1. The decorative brass handles on the hardware
Addressed and approved in March, 2010
1A holding the upper bookcases closed are
OK Photograph transmitted to manufacturer for
systematically coming off.
response and action
Pictures Item 1 / September 8 List: Pagel-4
The small screw pins holding the handles to the
Addressed and approved in March, 2010
1B rods are not only backing out, but also shearing
OK Photograph transmitted to manufacturer for
off.
response and action
Pictures Item 1 / September 8 List: Pagel-4
These handles require a solution and correction
Addressed and approved in March, 2010
1C using custom pieces so that they will not continue
OK Photograph transmitted to manufacturer for
to come off.
response and action
Pictures Item 1 / September 8 List: Pagel-4
in the alternative an additional $50,000 payment Our client, Molyneux Studio, was charged at cost
NO
1D for the handles would be acceptable and they will for the decorative hardware, less than
not
become Mr. Epstein's issue; $50,000.00 for all decorative hardware including:
acceptable
No Pictures hinges, espagnolettes, pulls & handles ...
2. The concealed hardware inside the swinging Approved in March, 2010
2A bookcases at the entry doors is falling off. OK Photograph transmitted to manufacturer for
Pictures Item 2 / September 8 List: Page 5 to 14 response and action
The screws are too short for proper attachment to Addressed and approved in March, 2010
2B the wood. . OK Photograph transmitted to manufacturer for
Pictures Item 2 / September 8 List: Page 5-14 response and action
2C The keys that operate the locks are breaking Not an issue in March, 2010
OK Photograph transmitted to manufacturer for
Pictures Item 2 / September 8 List: Page 5-14
response and action.
INTENTIONALLY OMITTED- SEE BELOW REMOVED
2D escutcheons at the keyholes are missing from INTENTIONALLY OMITTED SEE BELOW
Punch List NEW ORDER
NEW ORDER
24 EAST 64TH STREET
NEW YORK. NY 10021
212 935 6537 fax III 935 6538
iafoefaneellilearliag.tem ST) - Resolution Agreement - Oct 2010 Page 2 / 22
wriv.rANctuu- PANE LING .COM
EFTA00721947
PANELING
ITEM # ITEM DESCRIPTION - SEPT 08 PUNCH LIST ITEM STATUS COMMENTS
The hinges on the swinging bookcase doors are Not an issue in March, 2010
3 misaligned and require corrective action. Bookcase used as concealed opening. Technical
Issue linked to the type of design concept
Technical
ordered. We can work on the issue and -
Limitation
Pictures Item 3 / September 8 List: Page15-18 somewhat improve it - but a perfect, flush and
even alignment of swinging bookcases is not
technically possible.
The connecting hardware at the sliding panels at
4 the picture window is loose or broken OK
New replacement mechanism has been ordered
Issue will be fixed.
Pictures Item 4 / September 8 List: Page19-20
The wood filler pieces at the perforated frames
Addressed and approved in March, 2010
around the sliding panels at windows require open
5 The frames around the sliding panels as designed
joints to be filled so daylight does not shine OK
were intended to allow daylight to shine through
through.
Holes on carved frames can be filled in.
Pictures Item 5 / September 8 List: Page 21-22
6A Open joints in the woodwork, Addressed and approved in March, 2010
Especially at the cornice allow the cove lighting to We can address the issue but there are
6B shine through and must be filled. limitations to our intervention:
1. Philosophy of the design concept requested:
to look like 200 years old woodwork that has
Design
been salvaged from the depth of the sea.
Concept
2. Consequence of humidity damage from on
Pictures Item 6 from September 8 List: Page 23 to 37
site extended exposure to high humidity
levels
3. Prospective contraction and expansion of
wood at the sea side location
Numerous carved pieces of wood at the cornice
7 top edge are broken off and require repair and OK Addressed in March, 2010 and approved
replacement. Will fix the elements showed in pictures
Pictures Item 7 / September 8 List: Page 38-40
24 EAST 64TH STREET
NEW YORK. NY 10011
211 935 6537 fax Ili 935 6538
iafeefaarellilearliag.tem ST) - Resolution Agreement - Oct 2010 Page 3 / 22
WWW.TANCELLI-PANELING.COM
EFTA00721948
PANELING
ITEM # ITEM DESCRIPTION - SEPT 08 PUNCH LIST ITEM STATUS COMMENTS
Several cabinet doors require adjustment to fit Not an issue in March, 2010
8 evenly and square within their frames. Hinges and Espagnolettes created for the project,
Design are replicas of 17 century technology, not
Concept allowing for the adjustments that are possible
& with contemporary devices.
Pictures Item 8 / September 8 List: Page 41-46 Technical Alignment issue can be addressed and somewhat
Issue improved - client request for alignment is not a
feature of the chosen hardware technically
cannot be 100% fulfilled
INTENTIONALLY OMITTED SEE BEI Ow REMOVED
9 The perforated panels at the tilt top desk panels from INTENTIONALLY OMITTED SEE BELOW
Punch List NEW ORDER
NEW ORDER
INTENTIONALLY OMITTED SEE BELOW REMOVED
10
Shutters exterior sides from INTENTIONALLY OMITTED SEE BELOW
Punch List NEW ORDER
NEW ORDER
Not in Punch List INTENTIONALLY OMITTED SEE BELOW REMOVED
No item #
Columns seams cracks Not In INTENTIONALLY OMITTED SEE BELOW
Punch List
Not in Punch List INTENTIONALLY OMITTED SEE BELOW REMOVED
No item #
Carver signature on column Not In INTENTIONALLY OMITTED SEE BEJ OW
Punch List
No item # Not in Punch List Color Staining
NEW ORDER NEW ORDER
24 EAST 64TH STREET
NEW YORK. NY 10021
211935 6537 fax In 935 650
ish@faxcellilexeling.rem STJ - Resolution Agreement - Oct 2010 Page 4 / 22
WWW.FANCELL1-PANELING.COM
EFTA00721949
PANELING
2 OUTSTANDING ARREARS PAST DUE TO REMIT PRIOR TO TRAVEL PLANS
Description Terms of payment Currency
Balance on Executed approved work
Invoice 1000/0
"Work Complement" €22,500.00
#1098 prior to departure
Spring 2009
Invoice Travel expenses 100%
$18,618.00
#1096 May - June 2009 prior to departure
See Attachments copies of Invoices
3 NEW WORK: OUTSIDE PUNCH LIST
NEW COLOR STAINING PHASE ONE: SAMPLE DEFINITION
Estimate
Phase One: Sample definition Terms of payment Currency
# 2013
Required Molyneux Studio Designer on site
with Finisher for of process and color
approval
1000/0 on order €1,900.00
New Color - Sample Definition
1 person
2 days
€950 / per Day per Person
Supervision from Fancelli
for approval and signature
1 person 1000/0 on order €2,400.00
2 days
€1.200.00 / per Day per Person
Crew - Expenses
2 person
1000/0 on order $1,520.00*
2 days
$380.00 / per Day per Person
Air Fare
100% on order $3,800.00*
$ 1,900.00 per Person
* Note Expenses are estimated for a Low Season Basis
24 EAST 64TH
NEW YORK. NY 10021
III 935 6537 fa 212 935 653E
isfrefericelli ST) - Resolution Agreement - Oct 2010 Page 5 / 22
WWWFASULLI PANCL1NOCOM
EFTA00721950
e.%/leet
PANELING
4 NEW WORK: OUTSIDE PUNCH LIST
NEW COLOR STAINING PHASE TWO: PROJECTED LABOR STAINING
Following the definition of the staining sample PHASE ONE we will be able to assess the
amount of work necessary to execute the finish expected.
The intervention is also likely to require some de-installation of cornices and columns
Please find below an "estimated" price range / bracket
Estimate Amount Range
NEW COLOR - ESTIMATED LABOR Terms of payment
ft 2014 FROM TO
Projected New Color - Staining Labor
80% on order
€950 / per Day per Person
20% on €19,000.00 €22,800.00
NEW COLOR
4 persons
completion
LABOR
20 to 24 days
Projected New Color - Carpenter Labor
80% on order
€950 / per Day per Person
20% on €13,300.00 €39,900.00
2 persons
completion
7 days to 21 days
NEW COLOR - PROJECTED EXPENSES
New Color - Expenses Staining Crew
$380.00 / per Day per Person
100% on order $30,400.00 $36,480.00
4 persons
20 to 24 days
Staining Crew Flights
NEW COLOR - EXPENSES
$1,900.00 / per Person 100% on order $7,600.00 $7,600.00
4 persons
New Color - Expenses Carpenter Crew
$380.00 / per Day per Person
100% on order $5,320.00 $15,960.00
2 persons
7 days to 21 days
Carpenter Crew Flights
$1,900.00 / per Person
2 persons 100% on order *$3,800.00 *$3,800.00
*air fare can be shared with color
staining intervention for carpenters
NEW COLOR — SUPERVISION & APPROVAL
New Color - Supervision from Fancelli
SUPERVISION
for approval and signature
NEW COLOR
1 person 100% on order €2,400.00 €2,400.00
2 days
€1.200.00 / per Day per Person
Air Fare
100% on order $1,900.00 $1,900.00
$ 1,900.00 per Person
* Note Expenses are estimated for a Low Season Basis
24 EAST 64TH
NEW YORK. NY 10021
III 935 6 537 fax 211. 935 653E
infr@fancelli STl - Resolution Agreement - Oct 2010 Page 6 / 22
VIIMIANCEM-PANCLING.COM
EFTA00721951
tWitlela
PANELING
5 NEW WORK: REMOVED FROM PUNCH LIST
MARQUETRY
Item # REMOVED FROM Punch List NEW ORDER
The exterior sides (the side facing out Outside the scope of the Purchase
and viewable from the exterior when Order. Both sides of the sliding panels
looking into the windows) of the were to receive leather upholstery.
10 sliding panels are completely
unfinished and look like mere We have designed and submitted a
plywood. They are incomplete and pricing to Molyneux Studio for
need to be completed. marquetry, Pricing below estimate
#2010
No
Item 10 / September 8 List: No Pictures Alternatively, we can furnish and install
Pictures
an oak veneer
Marquetry for Shutters Terms of payment Currency
500/0 on order
Marquetry for Shutters
30% prior to delivery €47,992.00
Production Shipping Installation
20% at completion
Marquetry for Shutters - Expenses
2 persons
100% on order $3,800.00*
Estimate 5 days
it 2010 $380.00 / per Day per Person
Air Fare
$ 1,900.00 per Person
2 persons 1000/0 on order *$3,800.00*
*air fare can be shared with color
staining intervention for carpenters
* Note Expenses are estimated for a Low Season Basis
6 NEW WORK: REMOVED FROM PUNCH LIST
ESCUTCHEONS
Item # REMOVED FROM PUNCH LIST NEW ORDER
and the escutcheons at the keyholes Escutcheons plates are not part of the
2D are missing design. Existing Brass Key holes filets
Intentionally omitted see below have been approved
Designer to provide escutcheons
design approved by client.
Pictures Item 2 / September 8 List: Page 5-14
Manufacturer will be contacted for
pricing and schedule
24 EAST 64TH STREET
NEW YORK. NY 10011
Ill 935 6537 fax 111 935 6538
ifffe@facellipmeling.com ST) - Resolution Agreement - Oct 2010 Page 7 / 22
FAACELLI-PANELING.COM
EFTA00721952
l'ANFLINU
7 NEW WORK: REMOVED FROM PUNCH LIST
PERFORATED PANELS AT THE TILT ToP DESKS
Item REMOVED FROM PUNCH LIST NEW ORDER
The perforated panels at the tilt top
desk panels are consistently
Existing design was approved.
unfinished on the right side. The
As per sent and attached technical
perforations on the left side are
report image - the proposed solution
shaped like flower petals, while the
9 perforations on the right are simply
needs approval from designer and client
The new panels production with
drilled. The photo of the Escorial
matching perforations will be
Library and the shop drawings
accomplished without cost.
indicate the perforated panels are to
A priring for on site installation labor
match on each side.
will be provided.
No
Item 9 / September 8 List No Pictures
Pictures
8 NEW WORK: ILLUSTRATEDNOT IN PUNCH LIST
COLUMNS SEAMS CRACKS
Item tt REMOVED from Picture Log List Not in September 8th punch list
Not in o Philosophy of the design concept
Punch Columns seams cracks requested: to look like 200 years
List old woodwork that has been
salvaged from the depth of the sea.
o Consequence of humidity damage
from on site extended exposure to
Item / September 8 List: Page 47 to high humidity levels
Pictures
SO o Prospective contraction and expansion
of wood at the sea side location.
Repair cannot be ancticipated to be
permanent
9 NEW WORK: ILLUSTRATEDNOT IN PUNCH LIST
CARVER SIGNATURE ON COLUMN
ITEM# REMOVED from Picture Log List Not in September 8w punch list
Not in
Punch Carver signature on column This is the wood carver original
List signature, part of the work.
Pictures Item / September 8 List: Page 51
24 EAST 64TH STREET
NEW YORK. NY 10011
Tii 9)5 65)7 fax ITT 9)5 65)13
infr@facellipmeling.com ST) - Resolution Agreement - Oct 2010 Page 8 / 22
ramFAACELLI-PANELING.COM
EFTA00721953
e711/ZCee
PANELING
NOTES BELOW
Extension of Work Period: any extension will be estimated and payable 100% prior to
the extension
Humidity levels will be checked on site at the time of sample production to
confirm that color staining intervention is possible
Apart from Fancelli crew and Fancelli subcontractors, no other work and dust producing
activities can be executed as we work on the room.
Notice of completion will be given 6 days prior to work completion and Work Approval
must be received in writing, within 3 days of notice of completion. Work
Approval will be provided by Molyneux Studio, following the format previouly
used [March 22nd 2010] [Illustrated, referencing punch list itemization, and
approval comment].
Not Included: 2 movable scaffoldings required - provided by client.
Not Included: Client to provide transportation to and from Little St James Monday to
Saturday
As per previous intervention, work schedule Monday to Saturday full day
Included: Material - send on site Shipment of paints, colors, protection equipment
All expenses are estimated for a Low Season Basis and will be adjusted to the
intervention period.
24 EAST OATH
NEW YORK. NY 10021
III 935 6537 fax III 935 653E
ish@fancelliteneling.rom ST) - Resolution Agreement - Oct 2010 Page 9 / 22
IITIVC.FAACEILI PANUANG.COM
EFTA00721954
PANELING
PUNCH LIST SEPT 8th 2010 Sent from my BlackBerry wireless device
From: Jeffrey Epstein
Date: Wed, 8 Sep 2010 09:16:48 -0400
To: ja>
Subject:
1. The decorative brass handles on the hardware holding the upper bookcases closed are systematically
coming off. The small screw pins holding the handles to the rods are not only backing out, but also
shearing off. These handles require a solution and correction using custom pieces so that they will not
continue to come off. In the alternative an additional $50,000 payment for the handles would be
acceptable and they will become Mr. Epsteins issue;
2. The concealed hardware inside the swinging bookcases at the entry doors is falling off. The screws are
too short for proper attachment to the wood. The keys that operate the locks are breaking and the
escutcheons at the keyholes are missing.
3. The hinges on the swinging bookcase doors are misaligned and require corrective action.
4. The connecting hardware at the sliding panels at the picture window is loose or broken
S. The wood filler pieces at the perforated frames around the sliding panels at windows require open joints
to be filled so daylight does not shine through.
6. Open joints in the woodwork, especially at the cornice allow the cove lighting to shine through and must
be filled.
7. Numerous carved pieces of wood at the cornice top edge are broken off and require repair and
replacement.
8. Several cabinet doors require adjustment to fit evenly and square within their frames.
9. The perforated panels at the tilt top desk panels are consistently unfinished on the right side. The
perforations on the left side are shaped like flower petals, while the perforations on the right are simply
drilled. The photo of the Escorial library and the shop drawings indicate the perforated panels are to
match on each side.
10. The exterior sides (the side facing out and viewable from the exterior when looking into the windows)
of the sliding panels are completely unfinished and look like mere plywood. They are incomplete and need
to be completed.
fl11 1.41141014 ** ** 1.114.1 14.1 11 1.41.4.114.1 14.1 11 1.4 **** At ** **
The information contained in this communication is confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for the use of the addressee. It is the property of Jeffrey
Epstein Unauthorized use, disclosure or copying of this communication or any part thereof is strictly
prohibited and may be unlawful. If you have received this communication in error, please notify us
immediately by return e-mail or by e-mail to and destroy this communication and
all copies thereof, including all attachments.
24 EAST 64TH STREET
NEW YORK. NY 10011
212 935 6537 fax ITT 935 6538
infr@facellipmeling.com STJ - Resolution Agreement - Oct 2010 Page 10 / 22
WWW.FANCELLI-PANTLING.COM
EFTA00721955
PANELING
Pictures document = see attachment
Item 1 from September 8 List:
Page 1 to 4
Decorative Brass hardware Loose or broken
Item 2 from September 8 List:
Page 5- to 14
Concealed hardware at swinging bookcase is falling off
Breaking keys
missing escutcheons
Item 3 from September 8 List:
Page 15 to 18 included
Hinges on swinging bookcases are misaligned
Item 4 from September 8 List:
Page 19 to 20
Sliding panel rail broken
Item 5 from September 8 List:
Page 21 to 22
Light in the carved shutters frames
Item 6 from September 8 List:
Page 23 to 37
Open joints in woodwork
Light come through at cornice
Item 7 from September 8 List:
Page 38 to 40
Cornice missing elements
Item 8 from September 8 List:
Page 41 - to 46
Alignment of cabinet doors
Item 9 from September 8 List:
Perforations
o No pictures
Columns Seams/Cracks/Words Carved In Columns:
Page 47 to 50
CARVER SIGNATURE
NOT in the PUNCH LIST
Page 51
24 EAST 64TH
NEW YORK. NY 10021
935 6537 fax III 935 651E
infr@fancellitentliffig.com Sll - Resolution Agreement - Oct 2010 Page 11 / 22
IIWW.FANCULI-PANCLING.COM
EFTA00721956
e711/ZCee
PANPILING
Date: September 24, 2009 Invoice 1096
Molyneux Studio
29 East 69th Street LSJ Expenses
New York, NY 10021 Job Reference:
(212) 628-0097 With Receipts
Dear Pascal and Jeremy:
Please find below Invoice 1096 with justification receipts of the travel
expenses for the period May 18 - June 24, 2009
Receipts reference is indicated in the Item# column
Copy of receipts are to be found in PDF attachments
Thank you to let me know if you need further assistance
Best regards,
Christian Barthod
LS) Installation Expenses
From May 18th to
To June 21g, 2009
Item Nature Description Amount $
ARCarredo SAS di
Francesco Guerazzi
Invoice [€ 5.264.24=]
May 18 - June 21 2009 Airfare 4 installers. Italy — St. Thomas
ArcArredo -2009-Sep-04 $ 7,451.00
Food Meals, Groceries and Linens $ 2,661.25
Transportation Car Rental, gas $ 2,134.00
Transportation Tip Driver $120.00
Jean Pierre Fanelli
June 17 - 24, 2009 Teresa Travel Airfare Paris - USVI $1,173.00
June 17 — 21, 2009 Receipts as pdf Food meals $454.00
David Collins
6E-1 Estate Nazareth
May 18th - June 21st Invoice #51409 House Rental St. Thomas, USVI 00802 $4,625.00
TOTAL DUE USD $18,618.00
Note: C= USD 1.41541 at June 1 09
24 EAST 64TH
NEW YORK. NY 10021
III 935 6537 fax III 935 6538
infr@fewellitantliffig.com STJ - Resolution Agreement - Oct 2010 Page 12 / 22
WWW.FANCZILI-PANCL1NOCOM
EFTA00721957
e711/ZCee
PANELING
September 30, 2009 INVOICE 1098
1065 - D
Estimate
Jig email 05/09/2009
Work order 8321
Molyneux Studio
29, East 69th Street
New York, NY 10021
St. James
(212) 628-0097 Job Reference:
complements
Attn: Auralien Gallet:
Amount
Article Description U Qty
EUROS
Facing Panels for vestibule doors adjusted to existing
embrasure.
Decorative Hardware Not Included
Woodwork complements and fillers
to conceal gaps between woodwork and building
construction discrepancies. see report #10-A pictures
1
Large bay window;
2 windows;
2 entrance doors embrasures
Cabinet door replacement with Bamboo grill doors
2
Decorative Hardware Not Included
Color staining and finish of the above 1
On site installation 1
Total production 040,000.00
TRAVEL & LIVING EXPENSES
Estimated price. Le remboursement des frals de
voyage et de sejour engages pour le personnel devant se
deplacer dans la limite du budget de 13000€ que nous
avions calcul€ ;
Refund of travel expenses and sojourn - food
accommodation will be charged AT COST at the end of
stay - estimated 013,000.00
TOTAL 040,000.00
Mr. Molyneux requested to consider the options to Block shutters' cut out to create absolute
darkness in the room.
Work to be performed & to schedule:
o Wood work complement - upon approval
o Color finish touch up
Color touch up - and wood work complement can be done after the completion of the large
window bay and parquet floor.
24 EAST 64TH
NEW YORK. NY 10021
TIT 935 6537 fax III 935 653E
isfr@fericellitentling.com - Resolution Agreement - Oct 2010 Page 13 / 22
WWWFASCULI PANCL1NG.COM
EFTA00721958
e.9il/Zeet
PANELING
As per Jean Pierre Fancelli Email:
From: Jean Pierre PORTABLES [mailto: J
Sent: Sat 05/09/2009 00:52
To: Aurelien Gallet
Subject: LS]
Cher Aurellen ,
pour faire suite à notre conversation Je propose à Mr Molyneux un forfait de 40 000€
pour les travaux décrits dans notre dernier devis ;
Le remboursement des frais de voyage et de séjour engagés pour le personnel devant se
déplacer dans la limite du budget de 13000€ que nous avions calculé ;
J'espère que cette proposition sen agréée par Mr Molyneux , restant à votre disposition,
veuillez accepter mes meilleures salutations
lean Pierre Fancelli
24 EAST 64TH
NEW YORK. NY 10021
III 935 6537 fax III 935 6538
infreenrelli•peneling.rom - Resolution Agreement - Oct 2010 Page 14 / 22
WA.FANCEILI-PANCLING.COM
EFTA00721959
5il/Zeet
PANELING
Date: September 27, 2010 Estimate 201'
Work order Waiting
Molyneux Studio
750 Lexington Avenue
New York, NY 10022 St. James Office
Job Reference:
(212) 628-0097
VIA EMAIL Juan Pablo Molyneux
QtY Description Amount
Motifs marquetés sur portes dérobées des bibliotheques, volets coulissants aux deux
extrémités de l'office, Volets Coulissant sur grande baie
Suivant dessins proposéI7 Septembre 2010
Approvél7 par Molyneux Studio confirmation de Cesar 20 septembre 2010
Etude des motifs marquetés réalisation de dessins pour répartition des essences
1,200.00 E
de bois
Façades des portes dérobées et volets coulissants aux deux extrémités de
l'office
coté office et contre face à motifs de damiers en marqueterie en chêne avec fil
8 de bois alternés , filet noir de 2mm ,plate bande de 5 cm au pourtour de la 14,000.00 €
composition avec filet noir et filet de bois clair de 4mm. Dim 1739x900
Volets Coulissant sur grande baie
face office et contre face même travail à damiers en marquèterie de 1964x1742
2 6,840.00 E
avec filet et plate bande
2 volets latéraux face office et contre face même travail à damiers en
4 6,600.00 E
marqueterie de 1964x749 avec filet et plate bande
Marquêterie,
96 motifs marins en marqueterie suivant dessin repartis sur les faces à damiers 10,272.00 €
mise en caisse Transport a St. Thomas
1,380.00 €
Livraison sur site a St. James a la charge du client
Pose et finition sur place 8,900.00 €
TOTAL SOLUTION DE BASE 47,992.00 €
Option Moins Value -5,500.00 €
Variante en moins value : la face et contre face des volets de la baie vitrée
marquetés à damiers, contre face des portes dérobées et volets coulissants aux
deux extrémités de l'office, en chêne de fil , sans damiers marquetés
TOTAL SOLUTION en Variante 42 492,00 E
24 EAST 64TH
NEW YORK. NY 10021
In 935 6537 flw III 935 6538
infie@fenrelliteneling.com STJ - Resolution Agreement - Oct 2010 Page 15 / 22
WA.FANCEILI-PANCLING.COM
EFTA00721960
PANELING
Message transféré --------
De : <cesar@molyneuxstudio.fr>
Date : 20 septembre 2010 10:40
Objet : Little st james
: can ierre fancelli >, JPM Mobile
M Fancelli,
M Molyneux me demande de vous dire que M Epstein a aime et approuve le sketch des
voles.
M Epstein a souligne qu'il vous attend avec votre equipe le 23 sur Pile.
Merci de nous confirmer votre presence a la date du 23.
Merci
Cesar
Ce message a été envoyé depuis un terminal BlackBerry de Bouygues Telecom
24 EAST 64TH
NEW YORK. NY 10021
III 935 6537 fax III 935 6538
isfreenrelli•parteling.rom - Resolution Agreement - Oct 2010 Page 16 / 22
ennr.rAnctiu PANELING.CON
EFTA00721961
e.9il/Zeet
PAN(LING
,
6 c.".ce
ererortiec;
kc
\ r
es _e_O3,„(_
_ . saa.` Site
Conditions : accord sur présent devis, suivant sketsch approuvé.
Acompte de 50 % a l'acompte
Exécution 4 semaines à partir de la commande
Transport par avion en caisse bois
24 EArr 64TH
NEW YORK. NY 10021
In 935 6537 far III 935 6538
isfrenrelliteneling.com ST) - Resolution Agreement - Oct 2010 Page 17 / 22
WWW.FANCEILI PANELING.COM
EFTA00721962
gil/Zeet
PANELING
Date: October 26, 2010 a Estimate 2013
Work order Waiting
Molyneux Studio St. James Office
7
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 2d7e814f-1a31-4539-8a86-3e954f7198ec
- Storage Key
- dataset_9/EFTA00721946.pdf
- Content Hash
- cb49e65b7e1d3b15a3cf5f9cb1a1d443
- Created
- Feb 3, 2026