Zorro Projects - 6/15/13
Landscaping (22) - Start End Total Est. Cost Notes Photo
Rear Planter Bed 6/1/13 575,000.00 3/28/13 - Refurbishment & Maintenance proposals from 3
Front & Rear Parking Beds companies forwarded to RK & DI
Bowel Garden 4/27/13 - JE approved Aspen Landscaping for Refurbishment
Aspen Grove 5/9/13 - New proposal forwarded to JE & RK, awaiting direction
Pinion Screen 5/16/13 - Final proposal forwarded to RK, will discuss with JE
5/24/13 - Aspen agreed to $75,000
X
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started
6/8/13 - Work continues, soil preparation in progress
6/14/13 - Plant material starting to arrive, more due next week -
!attached photos
landscape Lighting Timers Replacement - Start End Total Est. Cost Notes Photo
$5,000.00 4/27/13 - JE approved
5/1/13 - Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location etc.
6/7/13 - Awaiting electrical proposal from RMC Electric
Landscaping - In House - Start End Total Est. Cost Notes Photo
Ponderosa Pines & Landscape Light:, at OS/1S 4/27/13 - JE approved the removal of-dad pine in courtyard &
Front Entrance Ponderosa Pines, Landscape Lights & relocate Pinions to the area.
6/3/13 - Project Started
6/7/13 - Removal of Ponderosa Pines complete
6/18/13 - Removal of courtyard Pine scheduled
EFTA01124639
Zorro Projects - 6/15/13
Terraces (27) - Start End Total En. Cost Notes Photo
Terraces - $52,000.00 4/7/13 $56,200.00 12/12/12 - Bid Received
Stucco/Gutters/Painting - $4,200.00 3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
X
i5/31/13 - There was a fault in one of the rolls of material, vendor
has reordered, will recover area once on site.
6/7/13 - Material on site, will continue 6/10/13
6/14/13 - Membranes & Gutters Complete - attached photos
6/18/13 - Stucco & Painting scheduled to start
Front Gates Openers Call Boxes (30) - Start End Total Est. Cost Notes Photo
4/20/13 - Bid received, requested vendor to make adjustments
5/9/13 - Received revised bid. Options & Equipment reviewed
5/12/13 - Options & Equipment selected, final bid due 5/21/13
5/21/13 - Final bid received via fax, unable to read, vendor will
resend.
6/8/13 - Final bid attached, also forwarded separately to RK.
6/11/13 - RK requested material breakdown
6/14/13 - Material breakdown forwarded to RK
Cooling Tower - (36) Start End Total Est. Cost Notes Photo
4/24/13 - RK approved bid from SPX & JBH. RK has all cost details
5/3/13 - Deposit was to be forwarded, awaiting confirmation
6/25/13 - Unit due on site
EFTA01124640
Zorro Projects - 6/15/13
Replacement of Pool Pac (33) - Start End Total Est. Cost Notes Photo
Engineering Inspection - $9,100.00 9/11/12 4/29/13 - Quote forwarded to RK, who requested more detail
Unit Cost - $43,170.00 5/8/13 - Revised quote forwarded to RK, awaiting direction
Camera Ducting Inspection - $1,214.91 5/22/13 - Beaudin Ganze on site to review project
Ducting - TBA 5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera.
6/3/13 -JBH forwarded estimate
6/4/13 -JE approved moving ahead
6/11/13 - JBH due on site
6/12/13 - JBH on site, completed camera inspection, awaiting
report
Repair Pool/spa (29) - Start End Total Est. Cost Notes Photo
$12,600.00 5/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
IF requested work.be completedan Sept
REQUIRE CONFIRMATION THAT BID IS ACCEPTED, SO VENDOR
CAN BE PLACED INTO SCHEDULE
Water Sample of Tap Water - Start End Total Est. Cost Notes Photo
6/12/13 4/27/13 - JE requested water samples be taken.
ads will be completed once water system is balanced
5/10/13 - Dakota RO Is down, pressure issues
6/2/13 -All Wells up and running
6/12/13 - Water samples taken. Results due back 6/24/13
Exterior Doors Main House - Start End Total Est. Cost Notes Photo
4/27/13 - JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
EFTA01124641
Zorro Projects - 6/15/13
Audio Upgrade - Start End Total Est. Cost Notes Photo
New N's 6/3/13 Installed - final programming required
DVD Players/Theater Upgrade Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before moving
forward
5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Breakfast Rm, Lodge & BH
6/12/13 - Gym, Lodge & BH Systems Complete
6/14/13 - Will exchange the Samsung DVD for a Marantz DVD in
Breakfast Rm
Kitchen Table Electrical - (35) Start End Total Est. Cost Notes Photo
Electrical & Data Cut In - $2,160.00 6/3/13 6/13/13 3/1/13 - Bid received Lead Time 1 Week
6/3/13 - Project Started
6/7/13
. . - Under floor conduit due to be completed 6/12/13 .
6/13/13 - Conduit installed, tiles replaced & grouted. Cat 5 still to
be pulled and punched down
Media Room Curtains (24) - Start End Total Est. Cost Notes Photo
Blackout & Rings 2/24/13 4/27/13 - JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
$6,262.08 5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) - Start End Total Est. Cost Notes Photo
Lined & Rings 2/24/13 4/27/13 - JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yardage
of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
$2,527.01 5/31/13 - AWAITING DIRECTION
EFTA01124642
Zorro Projects - 6/15/13
Gym - Mirrored Doors - Backed/Framed Start End Total Est. Cost 1 Notes Photo
2/24/13 3/4/13 - Project Complete. JE requested further work, which will
begin once Project 27 - Terraces complete
Phones Main House (31) - Start End Total Est. Cost Notes Photo
4/27/13 - JE approved installation of new phones at MH
Awaiting for service provision & estimated cost of delivery of
services - Project 21Microwave & IT
Microwave & IT - (21)- Start End Total Est. Cost Notes Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded detailsof RSM Craig
Franck. Brice has been in contact with Craig will forward details
5/24/13 - Received bid from Southwestern Wireless, have call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
6/8/13 - Forwarded TW Telecom Proposal for Delivery of Services
to JE & RK. Firm Bids due by 6/14/13
6/14/13 - Received bid from Southwestern Wireless, confirming
details before forwarding
6/15/13 - Informed JE, will forward once all details confirmed
Cell Repeaters & WI-Fl Start End Total Est. Cost Notes Photo
Cell Repeater - Library Will have installed 6/21/13
Cell Repeater - Gym Will have installed 6/21/13
Computers - Start End Total St. Cost Notes Photo
Lap Top - Lodge Requesting Approval to Purchase
Desk Top - RC Office Requesting Approval to Purchase
EFTA01124643
Zorro Projects - 6/15/13
Well K (37) - Start End Total Est. Cost Notes Photo
Plugging First Hole $15,000.00 Estimate to plug 1st hole
Lodge Roof Start End Total Est. Cost Notes Photo
Repair/Replace Broken Sections Three B's will complete while on site for upcoming projects
i
Tort - (23) - Start End ! Total Est. Cost Notes Photo
Replacement Walls/Roof/Door/Windows 5/9/13 $6,355.00 4/27/13 -JE approved Investigating options
plus shipping 5/9/13 - Project Request forwarded to RK & A
charges of 5/9/13 -JE approved Project, awaiting direction on deposit
approx. payment from RK
$480.00 5/13/13 - Deposit forwarded to vendor $3,177.50
6/24/13 - Removal of fumiture, deconstruction of existing
I walls/roof/windows & door to begin. Then reconstruction of base,
resanding/sealing floor required - in house
_ 7/3/13 - Scheduled Ship Date
Repair/Painting Work - ion Start End Total Est. Cost Notes Photo
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work that
will be required after MBR Terrace is completed
EFTA01124644
Zorro Projects - 6/15/13
Painting/Staining/Sealing - In House Start End Total Est. Cost Notes Photo
Hay Barn 5/13/13 6/14/13 5/13/13 - Project Started
5/24/13 - 90% - Staining of trim to be completed
5/30/13 - Work to start, due to high winds & stormy weather
X
work to continue 6/10/13
6/14/13 - Project Complete - attached photo
Bunkhouse 4/14/13 6/14/13 4/14/13 - Project Started
5/3/13 - 80% - Staining of trim & deck to be completed
5/30/13 - Work to start, due to high winds & stormy weather
X
work to continue 6/10/13
6/14/14 - Project Complete - attached photo
Bay Garages - including outside lights 5/13/13 6/14/13 5/13/13 - Project Started
5/24/13 - 90% - Staining of trim to be completed
5/30/13 - Work to start, due to high winds & stormy weather
X
work to continue 6/10/13
6/14/13 - Project Complete - attached photo
Fire House - including outside lights 5/13/13 6/14/13 5/13/13 - Project Started
5/24/13 - 80% complete
5/30/13 - Work to begin, due to high winds & stormy weather
X
work to continue 6/11/13
6/14/13 - Project Complete - attached photo
Stables - including outside/Inside lights 5/29/13 - Work to begin, due to high winds & stormy weather
work to begin 6/17/13
Yellow House Garage 6/12/13 6/14/13 6/12/13 - Project Started
6/14/13 - Project Complete
Log Cabin Work to begin once all painting/staining projects complete at RC
Lodge Work to begin once all painting/staining projects complete at RC
Reservoir Work be begin once all painting/staining/sealing projects complete
Fuel Storage Tanks Work to begin once all painting/staining/sealing projects complete
EFTA01124645
Zorro Projects - 6/15/13
RC Office Interior Work scheduled for Winter
Fuel Storage Tank Area - In House Start End Total Est. Cost Notes Photo
Removal of grass. Matting & edging to be
installed
Gravel/Edge Work RC Paths - In House Start End Total Est. Cost Notes Photo
All paths to be dug out, edged and gravel
to be installed
Log Cabin - In House Start End Total Est. Cost Notes Photo
Step Outside - Repair/Replace Broken
Section
Caboose -In House Start End Total Est. Cost Notes Photo
Installation of Retaining Wall
4 Bay Garages - In House St End Total Est. Cost Notes Photo
Repair Leaking Roof
Repair Damaged Wall
Pole Barn Water Truck Parking Start End Total Est. Cost Notes Photo
Installation of a Retaining Wall To begin late Fall, Early winter
Cactus Removal - In House Start End Total Est. Cost Notes Photo
Removal of Cactus to begin late Fall, early Winter
Vehicles
r
Start I End Total Est. Cost Notes Photo
2013 Ford Expedition - review Captain 3/27/13 5/2/13 - Estimate received - $11,528.74
Seats to be Installed / 5/31/13 - as of date unable to get a 2nd estimate,
Dogs I
Start End t Total Est. Cost] Notes Photo
4/27/13 - JE approved Investigating purchase of 2 dogs.
Researching
EFTA01124646
Zorro Projects - 6/15/13
Inventory/dean Work Shops - In House Start End Total Est. Cost Notes Photo
6/6/13 Work continues as time allows - complete clean up & Inventory of
all work shops at RC & MH
Purchases Start End Total Est. Cost Notes Photo
White Rug & Pad (26) - Gym (10 x 12) 5/16/13 6/14/13 4/27/13 -JE Robert's to manufacture a rug using carpet
used in M Office. Vendor no longer stocks this brand, will add
10% for spedal order.
5/15/13 - 2 Estimates received
5/16/13 - Estimate forwarded to JE - Enchantment Carpet X
5/16/13 - Project approved
6/8/13 - Rug on site
$862.55 6/14/13 - Project Complete - attached photo
Big Urns -Outside MH 4/27/13 -JE approved Terre Cotto constructed Urns
Outside Pool Furniture 6/22/13 - Will forward possible options
Pool Pace Clock 4/25/13 - Ordered, lead time 4 to 5 weeks
Large Chrome Pool Clock Investigating Options
Facial Machine to purchase
Wells- Dakota & K
Combined Usage as of date 6/14/13 6.33 afa
2014 Budget
Bunkhouse Start End Total Est. Cost Notes Photo
Window/Doors - Total Replacement
EFTA01124647
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 2960a5c8-b74d-4bf5-8632-34518e6992c5
- Storage Key
- dataset_9/EFTA01124639.pdf
- Content Hash
- edd882a2f3d17f95558b1c6befc2b1c3
- Created
- Feb 3, 2026