From: Richard Kahn <
Sent: Wednesday, May 11, 2016 5:18 PM
To: Jeffrey E.
Subject: Fwd: Zorro Ranch / CenturyLink Quote
Attachments: image001.png Untitled attachment 00076.htm; Untitled attachment 00079.htm;
HEMC_40MHz_Link details_2016.04.25.pdt Untitled attachment 00082.htm; Zorro
Ranch 1 GBPS MW Quote - 042516.pdt Untitled attachment 00085.htm
i finally heard back from Hector this morning who did not =ave any concerns about attached quote from future tech he
=id pose a few questions (see below)
quote attached is for 104,431 (travel and =odging not included estimated at 15,000) there is =pproximately 15,000-
20,000 of equipment and labor that will not be =eeded if sandia to main house works however this will only be known
=fter field site survey is completed attached =imeline was from 2.5 weeks ago which will push completion date to
=pproximately 2nd week of July if you want to =roceed i would like to begin process soon so everything is complete
=efore your August visit note - i also will attempt =o negotiate bid once you give me direction please =dvise thank you
Sequence of Events:
1. </=>Week of 4/25/16
a. FT provide quote to Zorro Ranch (4/25/16)
b. Zorro Ranch review quote and approve (1-2 days)
c. Future Tech to start the FCC licensing process
• &=bsp; &nb=p;i. Upon written approval of quote
• &=bsp; ii. Process will take 1 week to get initial channels =ssigned
• &=bsp; iii. Entire licensing process will take 4-5 weeks
d. Zorro Ranch issue PO and provide payment (1-2 days)
2. </=>Week of 5/2/16
a. FCC provide conditional channel approval
• &=bsp; &nb=p;i. Remaining period of time is just paperwork process to =inalize license
b. Future Tech order equipment based off of conditional =hannel approval to get order in process
• &=bsp; &nb=p;i. 4-6 week lead time after receipt of order
3. </=>Week of 5/9 or 5/16
a. Future Tech to conduct Field Site Survey
4. </=>Week of 5/23
a. Future Tech to complete field report
b. Future Tech to order consumable materials based upon field =eport
S. </=>Week of 6/16 (Estimated based upon the above chain =f events and equipment lead time)
a. Deploy to market to install solution
Please note =he above is a HIGH LEVEL timeline to help provide an outline for the =ath =orward.
</=iv>
EFTA_R1_02081523
EFTA02703456
Richard Kahn
HBRK Associates Inc.
575 Lexington =venue 4th Floor
New York, NY 10022
tel =
fa
cell
From: Hector Cintron mailto >
Subject: RE: Zorro Ranch / CenturyLink =uote
Date: May 11, 2016 at 5:33:01 AM EDT
To: Richard Kahn < <mailto: >
Cc: Brice Gordon < <mailto >
Hi =ichard,
Is there anything =pecific that you have concerns? Everything looks fine but just a =eminder, just like GSJ, I'm
more in the configuration aspect and not =he physical installations.
Also depending on what your future needs =re:
what are your internet =andwidth plans for 2-4 years
is the internet for only =he main residence?
Are there plans to =edistribute in other parts of the ranch?
From: [mailto
Sent: Friday, April 29, 2016 12:40
To: Hector Cintron
Cc: Brice Gordon
Subject: Fwd: Zorro Ranch / CenturyLink Quote
Email =eceived from outside of the ATN domain. Use caution before using =inks/attachments.can you please
review attached and provide us =ith your thoughts
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington =venue 4th Floor
New York, NY 10022
tel
2
EFTA_R1_02081524
EFTA02703457
fax
celIM
Begin forwarded message:
From: =/b>Richard Kahn <I==a>
Subject: =/b>FW: Zorro Ranch / =enturylink Quote
Date: April 25, 2016 at 6:25:27 PM EDT
To: =/b>leffrey Epstein <jeevacation@gmail.com>
From: Chris Cappiello =It <mailto
Date: Monday, April 25, =016 at 6:08 PM
To: Richard Kahn
Cc:
>, Dave Rumore , Peter Cappiello
, Walter Tanner , Chris Cappiello
Subject: RE: Zorro Ranch / =enturyLink Quote
Hey Richard.
I hope all is well with you.
Per our discussion last week we have finalized =ur design for this project to support the requested 1
GBPS solution =rom Day 1. The incremental cost from 300 MB to 1 GB is all related to software =icensing costs on this
solution and is negligible to the total project. =n that basis we just designed this to 1 GBPS day one.
I have attached the link design for you and have =rovided a summary below.
Within this plan we would order the required =quipment (2 links + 1 spare set) and licensing (3 links) to
expedite =he delivery of service. If we were to try and break this into PLAN A and PLAN B it =ould delay things by a whole
order of magnitude and increase your cost =y more than the extra FCC license cost we are putting in day 1 ($4k
3
EFTA_R1_02081525
EFTA02703458
=nvestment to streamline the project). By taking this approach we can speed up the deployment timeline and cover all
our =ases so that when we come out to do the install we have the solution in =lace.
1. Primary Link Design
a. Sandia Crest to Main =esidence
&nb=p; =/span>11 GHz with 4' =ntennas
&nb=p; =/span>NOTE: If this "Primary =olution" is successful you would have 1
extra set of spare equipment =2 total), as the second link from ZDC Main to Main Residence would not be =sed.
2. Secondary Link Design
a. Sandia Crest to ZDC
&nb=p; =/span>11 GHz with 4' =ntennas
b. ZDC Tower to Main =esidence
&nb=p; i. =/span>11 GHz with 2' =ntennas
&nb=p; =/span>NOTE: if we were to go =ith secondary solution based upon the
primary solution not working from = line of site perspective, you would have 1set of spare equipment.
Quote Assumptions:
1. Travel costs — all =ravel costs (Flights, car rentals, hotel) to be billed back to customer =t cost +15%
2. Shipping costs — all =hipping costs to be billed back to customer at cost +15%
3. Permitting — the end =ser will handle any necessary permits (if required)
4. Consumables — the =ttached quote is an estimate and will be verified based upon site =urvey
5. Site Readiness — FT =ssumes that the sites have tower space, cabinet space for power =upplies,
power available and switch/router in place to take receipt of =ervice
Sequence of Events:
1. Week of 4/25/16
4
EFTA_R1_02081526
EFTA02703459
a. FT provide quote to Zorro =anch (4/25/16)
b. Zorro Ranch review quote =nd approve (1-2 days)
c. Future Tech to start the =CC licensing process
&nb=p; =/span>Upon written approval of =uote
&nb=p; =/span>Process will take 1 week =o get initial channels assigned
&nb=p; =/span>Entire licensing process =ill take 4-5 weeks
d. Zorro Ranch issue PO and =rovide payment (1-2 days)
2. Week of 5/2/16
a. FCC provide conditional =hannel approval
&nb=p; =/span>Remaining period of time =s just paperwork process to finalize
license
b. Future Tech order =quipment based off of conditional channel approval to get order in =rocess
&nb=p; =/span>4.6 week lead time after =eceipt of order
3. Week of 5/9 or 5/16
a. Future Tech to conduct =ield Site Survey
4. Week of 5/23
a. Future Tech to complete =ield report
b. Future Tech to order =onsumable materials based upon field report
5. Week of 6/16 (Estimated based upon the above chain of events =nd equipment lead time)
a. Deploy to market to =nstall solution
Please note the above is a HIGH LEVEL timeline =o help provide an outline for the path forward.
Thanks again for the opportunity, we look =orward to hearing from you.
5
EFTA_R1_02081527
EFTA02703460
Best regards,
Chris Cappiello
Director of Business =evelopment
Future Technologies =enture, LLC
P:
E: <mailto
6
EFTA_R1_02081528
EFTA02703461
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 291670e4-5651-4385-8127-c0953aaf53e1
- Storage Key
- dataset_11/EFTA02703456.pdf
- Content Hash
- bba383a8f31c0398a74b822d8c1f3157
- Created
- Feb 3, 2026