EFTA01198357.pdf
dataset_9 pdf 103.6 KB • Feb 3, 2026 • 2 pages
From:
To: Jeffre E stein <*eevacation ail.com>
Cc
Subject: ZDC Projects and Photos
Date: Sat, 27 Jun 2015 00:46:39 +0000
Attachments: Movie_Room_Equipment.JPG; Movie_Room_Equipment_2.JPG; Leather Panels.JPG;
Gym-Pool_Audio.JPG; Pool_Speakers.JPG; MH_Landscaping.JPG;
MH Landscaping_2.JPG; MH_Landscaping_3.JPG; MH_Landscaping_4.JPG; MH_Rugs-
Retumed.JPG; RC_Bunk House_Stucco 2.JPG; RC_Bunlc_House_Stucco_2(1).JPG;
RC_Bunk_House sIewWindows.JPG; 11C_Paint.JPG; RC_Paint_2.JPG; RC_Paint_3.JPG;
RC_Paint_4.JPG; RC_Picket_Fences.JPG; RC_Picket_Fences_2.JPG;
RC_Pickets_Fences_3.JPG
Jeffrey
Project Status and pictures for your consideration
Maio House
Movie Room:
New equipment install complete
Gun Cabinet panels leather inserts complete
Replacement subwoofer ready for install
Chaises, Chairs & Ottomans ordered, estimated delivery July 30th
Pool/Gym Sound System:
Complete
Great Room Sound System
Klipsch speakers needed new tweeters, ordered, expect delivery next week.
Separate e mailing regarding amps follows
Poolpak:
New compressor installed, still have operational issues
Will have more detail next week.
HVAC Controls:
Investigating second bid that allows will thermostat control.
Honey Well on sight 6/30 for sight inspection
Landscaai tg:
Hydroseeding complete
Pool Sod complete
Planter Beds, work to begin week of 29th June
Pruning Trimming of trees continues
Surge Protection:
90% Complete, 2 outstanding units due on sight next week.
Outdoor Rugs:
Rugs returned due to damage in shipping
New delivery date, last week of July.
Lodge
Power washed exterior surfaces,sealer is being applied
Outside Furniture in production
EFTA01198357
New Appliances ordered, delivery first week of July.
Landscape tidy up next week.
Ranch Central
Bunkhouse:
Exterior painting, porch & new trim complete
Interoir Painting of all rooms in progress
Sofa ordered, delivery estimated last week of July
Windows installed, exterior stucco repair week of June 29th
Outer Buildings:
Exterior Painting & Staining of workshops, garages, pole barn, hay barn. lire house complete
Painting of Picket Fences complete
Lardscpig:
Pruning/Trimming of trees complete
Cottonwood Trees x 6 mid July
Equipment/VehideS:
New Ride on Mower on sight
Tandem Trailer on site
Mercedes 5500, completion of paint work 3 July
LV Promtyi
Painting Fence line complete
Tennis Court Resurfacing, Color & lines complete, basketball lines to be completed next week
Other Items
New Skid installed, Shed refurbished & stained complete
All systems up & running, fully operational
Still having minor issues with Reservoir Clay valve operation, nothing critical.
Water Development:
WRD Field Inspection Monday 29th, 10 am
To confirm well locations ( GPS) and to view/photograph lands designated to be irrigated under the PBU for E 7871.
View plugged bore hole
WRD anticipates acting on application within a week of field inspection.
Casey Cook is recommending the construction of a irrigation pond.
The State need to advise if pond can has to be in the " Place of Use" or can be constructed outside this area.
We need OSE direction on pond location to confirm estimated cost of final 2 phases of this Project..
Brice Gordon
Stanley, NM
Ph:
EFTA01198358
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 251b9b9f-ef46-43dd-bdfd-c7b0e37bd0fe
- Storage Key
- dataset_9/EFTA01198357.pdf
- Content Hash
- bb467aa2ce465125aa5ea44542f24211
- Created
- Feb 3, 2026