EFTA00609244.pdf
dataset_9 pdf 936.9 KB • Feb 3, 2026 • 4 pages
LSJ CONSTRUCTION
Subcontractor Payout
Project: Main House January 6, 2010
Trade: Geotech
Requisition #2
Subcontractor Jaca & Sierra
Partial Final
X
Original Contract Sum: $6,800.00
Change Orders Submitted & Approved: $2,000.00
New Change Orders: $0.00
Total Work Contracted to Date: $8,800.00
Total Work Completed to Date: 100% $8,800.00
Less Retainage: $0.00
Total Payments Made to Date: $3,000.00
Total Current Payment Due: $5,800.00 ✓
Balance to Finish including Retainage: $0.00
Sales Tax Liability:
a. Subcontractor/Supplier is liable, explaiiinstall only / tax
included in contract
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company:
d. Shipping None
Total Outlays for this contract incl. Sales or Use Tax: $8,800.00
JEE approval attached Invoice Attached
YES NO YES NO
X X
Submitted Bill Approved by:
Signed: Signed:
Date: January 6, 2010 Date: January 6, 2010
Approved by: Emad Approved by:
Signed: Signed:
Date: \\-\\‘° Date:
45S 1011
0 1- -1
EFTA00609244
LSJ CONSTRUCTION
Project Main House
Jbcontractor • full legal name: Jaca & Sierra Date Revised: January 6. 2010
Phase tf 01.807
Trade: Geotoch
Invoice Requisition #2
Insurance expiation: Payment
Partial Final
X
Invoice/Re:Ill Dale C/0 Amount Retainago Duo Paid Date Paid Choddi Balance
Contract 10107/09 6.80000
CON1 12/29/09 2.00000
CO#2
CO#3
CO#4
.00#5
Requisition #1 10'27100 1000.00 3.000.00 3,000.00 0.00
Requisition #2 5.80000 5.800.00 5.800.00
Requisition #3 - 0.00
Requisition #4 -
(Total 8.800.00 0.00 8.80000 3.000.00 5.800.00
Contract Amount - Phase
contract 6.800 00 Geolechnical Exploration
COtil 2.000.00 Extra day of ailing to gel required borings
COQ Description
CO#3 Description
CO#4 Description
CO#5 Desorption
Contracted To Date 8.800.00
Balance of Contract w/Retainage
EFTA00609245
JACA & SIERRA TESTING LABORATORIES OR9WalgE
12/29/2009 I 07f7c7P7
LA
L.100 RED HOOK QUARTER r. A_ CONDITIONS
Upol:
THLIMP,-
Project :STRUCTURE LITTLE ST. JAMES, USVI
FOR SERVICES RENDERED AS FOLLOWS UNITPRICI AMOUNT
FOR THE PERFORMANCE OF A GEOTECHNICAL
EXPLORATION FOR THE PROPOSED STRUCTURE LITTL
ST. JAMES, USVI.
2 DAYS DRILLING CREW AND EQUIPMENT 2,000.00DAYS $4,000.00
1 LSUM MOBILIZATION INCLUDING AIRFARE 1,500.00LSUM $1,500.00
AND SOIL SHIPPING
1 DAY FIELD ENGINEERING $800.00DAY $800.00
20 HRS ENGINEERING TIME FOR 4125.00HRS $2,500.00
REPORT PREPARATION
Sub - Total 08,800.00
-83,600.00
TOTAL TO BE PAID
DEPOSIT c5:see.0
-t; jot )
iSidu
I n€RET C EMAATANDaWMUMAIMAT
?tit PA, ['UM()
EFTA00609246
JACA & SIERRA TESTING LABORATORIES DEWO0@lo,
12/29/2009 0036202 J
LAFAYETTE UUNTRAUTUH5, LLU
6100 RED HOOK QUARTER ST. A? CONUNriiNS
Upon Receipt
TWIMAH :0'.0.
Pic: loci :STRUCTURE. LITTLE ST. JAMES, USVI
FOR SERVICES RENDERED AS FOLLOWS
FOR THE PERFORMANCE OF A GEOTECHNIGAL
EXPLORATION FOR THE PROPOSED STRUCTURE LITTL
ST. JAMES, USVI.
DAYS DRILLING CREW AND EQUIPMENT 2,000.00DAYS 94,000.00
1 LSUM MOBILIZATION INCLUDING AIRFARE 1,500.00LSUM 91,500.00
AND SOIL SHIPPING
1 DAY FIELD ENGINEERING 1 9800.00DAY 8800.00
20 HRS ENGINEERING TIME FOR 8125.00HRS 52,500.00
REPORT PREPARATION
Sub - Total r 98,800.00
-93,000.00
TOTAL TO BE PAID $5,800.00
DEPOSIT
73ZICIV0CE
ear,A. necceve
is JUST AND CORRECT AND THAT
CUSTOMER
EFTA00609247
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 249d965c-2dc9-47b5-ab2b-6c4843c1ef09
- Storage Key
- dataset_9/EFTA00609244.pdf
- Content Hash
- 8768757b005441ecfd611c35cbcf2063
- Created
- Feb 3, 2026