72- WATER START END EST.COST NOTES PHOTO STATUS
DEVELOPMENT
5/6/2014 3/9/19 - Casey reported on readings - is about 29% of the total
PBU target of 68afa. With 33% of the year gone, Ranch is on target
Noting that since we started pumping harder in 2017, there has
been a steady decline in production, with about 40ft decline in
Water Levels since last year, but with continued monitoring and
working on giving all the Wells a long rest period after Nov all
should be good
96B - PAVING OF START END EST.COST NOTES PHOTO STATUS
ROADWAY
6/29/2017 2/12/19 - Gilbert Luna (Universal Paving) & his Forman On Site to
Review Final Section of Work. He Proposed Only to "Fix" 20001 -
MH Z to Bull Head. He indicated Fix for Office to Main Gates.
Proposed Work to begin March.
BG has concerns regarding "Fix" & Proposed Start Date, due to
Temps. Recommend late April/May. BG explained Owner would
want New Surface to Run from MH Z to Cattle Guard RC, Office to
Main Gates
BG indicated a payment of 100k, Gilbert Luna would need to sign
Legal Binder. He expressed concerns as requested work would
cost him approx. 100k. He was to review numbers & get back with
BG. As of date & time no contact has been made.
Should we contact Mountain States or another Company to see if Awaiting
:they are interested in providing a Proposal for a "Fix"? Response
3/18/19 - Received letter from Calvert & Menicucci - collections
agency for Universal Construction, Inc. Forwarded to RK & DI. A
complete timeline & details of the Project will be forwarded to DI
PM 3/18/19
102 - LUTRON START END NOTES PHOTO STATUS
SYSTEM - MH
2/22/2019 I 3/12/18 - Lutron Rep On Site. Reviewed system with Randy from
RMC Electric. Existing system was designed for local control at the
physical switches not controlled by the Lutron system in the Mech
Rooms, therefore will be difficult, but not impossible to upgrade.
Lutron are reviewing the options and will forward details within 10
.days
118B PURCHASE START END EST.COST NOTES STATUS
WATER TRUCK
Will review with JE when On Site
Page 1
EFTA00811088
1181: - PURCHASE START END EST.COST NOTES PHOTO STATUS
GRADER
Will review with JE when On Site
135 START END EST.COST NOTES PHOTO STATUS
REFURBISHMENT
RED HOUSE
•
1/21/2019 3/12/19 - Cabinets Installed, Shower/Tub Installed/Electrical Rough
In Complete/Tile Flooring Complete
3/17/19 - Granite Installed
;3/18/19 - Fireplace Installed - Stone Work to start 3/19/19
'3/22/19 - House Incorporated expected to be Complete with their
Work
3/25/19 - Carpet to be Installed
136 - REPAIR F150 START , END EST.COST NOTES PHOTO STATUS
2/7/2019 3/8/2019 $ 2,150.00 3/8/19 - Repairs Complete
Project Total $ _2; 150.09 Complete
137- START END EST.COST NOTES PHOTO STATUS
PURCHASE/INSTALL
FURNACE - STABLES
2/19/2019 2/28/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing Furnace. Furnish/Install 1 Carrier 110,000 BT Furnace in Response
Stables. (2/16/19)
2/16/19 - RK requested 10% Discount
$ 1,447.71 2/21/19 - 50% Deposit Paid to Airpro
2/27/19.7 Airpro Installed New Furnace
2/28/19 - Furnace Installed. Running 100%
$ 1,447.71 3/18/19 - Paid Balance to Airpro
Project Total 5 2,895.42 Complete
138 - START END EST.COST NOTES PHOTO STATUS,
PURCHASE/INSTALL
AC SPLIT UNIT &
FURNACE -
HOUSE
2/19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of Awaiting
Existing Swamp Cooler. Furnish/Install 1 Carrier 4 ton AC Split Unit Response
and Furnace to LVs House (2/15/19)
2/16/19 - RK requested 10% Discount
2119/19 - Airpro Discounted 10%
$ 4,896.99 2/21/19 - 50% Deposit Paid to Airpro
3/15/19 - 90% Complete, Awaiting Electrical Connect - 3/22/19
Page 2
EFTA00811089
139 - START END EST.COST NOTES PHOTO STATUS
PURCHASE/INSTALL
AC SPLIT UNIT &
FURNACE - YELLOW
HOUSE
2/19/20191 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of
Existing Swamp Cooler. Furnish/Install 1 Carrier 3 ton Furnace to
Yellow House
2/16/19 - RK requested 10% Discount
2/19/19 - Airpro Discounted 10%
I Awaiting
Response
(2/16/19)
$ 4,603.59 2/21/19 - 50% Deposit Paid to Airpro
3115/19 - 90% Complete, Awaiting Electrical Connect - 3/22/19
14C - START END EST.COST NOTES PHOTO STATUS
PURCHASE/INSTALL
X 6 UNIT HEATERS -
GARAGES RC
2/19/2019 2/12/19 - Proposal Forwarded to RK to Remove/Dispose of x Awaiting
Existing 6 Heaters. Fumish/Install 6 Sterling Unit Heaters - Response
Garages RC (2/16/19)
2/16/19 - RK requested 10% Discount
2/19/19 - Airpro Discounted 10%
S 8,841 43 2/21/19 - 50% Deposit Paid to Airpro
2/25/19 - Material/Parts Ordered. Installation expected 3/14/19
3/15/19 - Due to weather/road closures. Installation rescheduled
3/25/19
141 - START END EST.COST NOTES PHOTO STATUS
CARPET/TILE/WINDO
W TREATMENTS -
LODGE
2/11/2019 3/15/19 - Carpet/Tile Install Approved - JE
3/18/19 - Deposit paid for Carpet & Tile
3/18/19 - Furniture etc. removed from Lodge
3/19/19 - Native Son On Site to review window treatments
3/19/19 - Carpet to be removed
14? - PHONE SYSTEM • START END EST.COST NOTES PHOTO STATUS
LODGE & LOG
Project Placed On Hold 1/10/18
Are we still to proceed with Verizon Cellular Phone Line for Lodge? Awaiting
Response
Are we still to proceed with Verizon Celular Phone Line & Solar Awaiting
Generator for Log Cabin? Response
Page 3
EFTA00811090
143 - SECURITY START END EST.COST NOTES PHOTO STATUS
CAMERAS -FRONT
GATES
Existing Security Camera System has Failed. Gates Operational
3113/19 - Purchased Verizon Cellular Security Camera - 30 day trail
- 820.00 a month
3/14/19 - Camera Installed, at present linked to Brice, cell
phone & I Pad. Working very well. Will forward update 3/22/19
144 - SEPTIC EST.COST NOTES PHOTO STATUS
SYSTEMS -RC
2/28/2019 Septic Line to the Tank & the Leaching Field for the BH need
replacing. Roots from Trees have Compromised the Line. The
.Adobe is in the same situation
2/28/19 - All RC Septic Tanks. Pumped Out
Gene Basset will forward a Proposal for Removal/Installation New Awaiting
'Septic Tank by 3/22/19 Proposal
145 - GARAGE DOORS START PA) EST.COST NOTES PHOTO STATUS
-RC
Will Review when JE On Site
146 START END EST.COST NOTES PHOTO STSTUS
REFURBISHMENT
PICKET FENCES - RC
Repair & Painting of all Picket Fences - April 2019
$ 166.82 Purchased 100 Cedar Pickets - Curing in Garages
147 - SITE WALLS & START END EST. COST NOTES PHOTO STATUS
MISC PLASTER
WORK MC
Expect Bid by 3/22/19 - Work would not start until late April/May
148 - NEW PATHWAY - START END NOTES PHOTO STATUS
LOG CABIN
2/15/19 - Existing Stone Pathway Removed
$ 3,144.39 2/20/19 - Deposit x 65 3x12x6 Rough Pine. A platform will need to
be constructed under pathway to keep it level
$ 1,287.69 3/7/19 - Balance Rough Pine
3/19/19 - Project to begin
Page 4
EFTA00811091
WINDSHEILD - 2002 Contacted Gary Mann (RK Contact). He contacted Mercedes Awaiting
MERCEDES reference Windshield Repair - Unable to come up with Solution. Response
Gary was to contact Guard Car Companies, have left a message
requesting update
COMPUTOR - James Ce forwarded History of Existing Library Computer, Feb 2015
LIBRARY - MH
How do you wish to proceed? Awaiting
Response
LANDSCAPE -EAST Once Weather Breaks Work will Start on Collapsed Section/Dry
GARDEN Stack Walls & Lavender Beds
Page 5
EFTA00811092
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 2314b0e3-064c-4a81-b5c2-dd6ed23c6f88
- Storage Key
- dataset_9/EFTA00811088.pdf
- Content Hash
- 49d97ef8cb6499dd1b30611bd7607d89
- Created
- Feb 3, 2026