EFTA00828421.pdf
dataset_9 pdf 116.8 KB • Feb 3, 2026 • 2 pages
From: "Jeffrey E." <jeevacation@gmail.com>
To: Richard Kahn
Subject: Re: Great St James
Date: Sat, 30 Apr 2016 15:30:12 +0000
as i told you i have a bid for 40k. my instructions are to source locally if i can. and save travel costs. I will
increase my offer to you . and for 50k . ok your work. amy dempsey is being retained for routing.
On Sat, Apr 30, 2016 at 11:23 AM, Richard Kahn < > wrote:
Sent from my iPhone
Begin forwarded message:
From: Hugo Hodge
Date: April 30, 2016 at 10:27:08 AM EDT
To: Richard Kahn
Subject: Re: Great St James
Good morning Mr.Kahn,
I have thoroughly reviewed your suggestions for modifications to the bid and given your request great
consideration. I honestly believe that the items you requested are important for a successful project. For
example, the witnessing of the factory acceptance is not a step I would recommend omitting.
With that said, the items you suggested to remove total $23,000. To ensure the integrity of this project I am
willing to do the project with the entire scope at the original price less $23,000 for a total of $80,000. If you
decline this option and are convinced that these items should be omitted, I am willing to reduce the
remaining items by 10% resulting in a cost of $72,000 for the revised scope.
I strongly recommend you consider the first option but I am willing to discuss this further with you if
necessary.
Best Regards,
Hugo Hodge Jr
On Thu, Apr 28, 2016 at 12:32 PM, Richard Kahn < > wrote:
it was a pleasure speaking with you earlier. as discussed the following areas are scopes that will not be
needed and my comments:
a) conceptual design on cable routes - ok to keep - please revisit pricing
b) detailed cable specs and preparation of bid docs - ok to keep - please revisit pricing
c) detailed switch and meter design and prep of all switches and metering device - ok to keep - please
revisit pricing
d) review all switch and cable bid submittals and submit to Wapa for approval - ok to keep - please revisit
pricing
EFTA00828421
e) witness factory acceptance test - not necessary as all we need isfor you to review testfrom manufacturer
and should be included in d) above
0 complete final design to include civil and electrical drawings - ok to keep - please revisit pricing
g) witness installation and test electrical devices - not needed
h) complete as builts - not needed
i appreciate your effort in revisiting your pricing and look forward to hearing back from you this afternoon
thank you
Richard Kahn
HRRIC Accnriatec Ino
New York, NY 1 0022
tel
fax
cell
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation@gmail.com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA00828422
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 21373a45-492f-4b1c-9eeb-1aab9260bdfa
- Storage Key
- dataset_9/EFTA00828421.pdf
- Content Hash
- e601ec8146d497b8bb44562f7ff5bb8c
- Created
- Feb 3, 2026