From: "William Murphy"
To: "Jeffrey Epstein" <jeevacation@gmail.com>
Cc: "Brice Gordon" , "William Murphy"
Subject:
Date: Tue, 25 Aug 2009 13:22:09 +0000
Attachments: ChoiceCommServiceProposal.doc; J_Epstein_St_Thomas_3M.pdf:
J_Epstein_St_Thomas_6M.pdf
Last September, we brought consultants from the communications company we use in New Mexico to Little St
James for a site survey. The purpose was to determine the best means of improving data delivery for our users in
St Thomas and LSJ. To date, there have been several inquiries made to bandwidth vendors in St Thomas with
none of them offering any rates better than $1000 per megabit (MB). I spoke to Richard Boltz (from the NM
Communications Company) today and he summarized our issue in this fashion:
Last mile using physical infrastructure (copper/fiber) will require Innovative.
Last mile services wirelessly will most likely be delivered through Broadband VI.
There are regular power issues at the Caprita point location where the equipment we need to deliver voice and
data to LSJ fails and service is interrupted.
At the Wireless Consortium in Vegas earlier this year, Richard made contact with CommNet who were interested
in delivering broadband services to St Croix. They were hoping to use LSJ as a relay in delivering bandwidth to
St Croix. Our cost for this project was extremely high as we were looking to implement WiMax on LSJ. WiMax
devices currently cost substantially more than WiFi devices and have yet to be an accepted standard in the US.
CommNet has recently contacted Richard to see if we are still interested in a partnership of sorts.
I have attached the estimates that we have received from Sprint for increased bandwidth. These quotes are for
bonded T l s delivered to Caprita Point.
ATT had verbally committed to being able to deliver 10Mbps to LSJ. When we pressed them for a commitment,
they claimed they would not be able to deliver their initial proposal because of lagging infrastructure upgrades in
Puerto Rico.
Since this process has begun, we have been met with incredibly slow turn around for any information. Most of
this is attributed to Innovative dragging their heels. Our initial contact to Sprint was made on the 3th of March
this year. Sprint was unable to deliver a documented quote until the end of May; nearly three months later. As
last mile services using the Caprita point utility pole will require Innovative copper, I would not expect their
customer service to ameliorate any time soon.
EFTA00776210
The initial "special" offer from Choice Communications was completely disregarded by myself and Brice as it
did not appear to provide any concessions to you or LSJ. I believe that they may need LSJ in order to deliver
services to St Croix and maintain their status as a competitive bandwidth alternative to Broadband VI; however,
contract negotiations will be required. We are going pursue this lead as this seems like the only option where we
are in a position to barter and deliver Internet service to LSJ at a reasonable cost. This alternative will get us
around the InnovativelBroadband VI last mile conundrum if we can find some middle ground.
The initial Choice Communications agreement and the Sprint quotes are attached.
William Murphy
Systems Administrator — HBRK Associates
EFTA00776211
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 1ce85bba-3b63-4c05-9b5c-b4982bb0ad78
- Storage Key
- dataset_9/EFTA00776210.pdf
- Content Hash
- 3baaedf14f6bbdb9c3b9f591cab13561
- Created
- Feb 3, 2026