EFTA01139593.pdf
dataset_9 pdf 275.9 KB • Feb 3, 2026 • 5 pages
From: Cecile de Jongh
To: Ann Rodriquez J E <jeevacation@gmail.com>, Rich Kahn
Subject: Fwd: fiber project
Date: Thu, 03 Dec 2015 20:10:50 4.0003
Inline-Images: image001.jpg; iniage002.jpg
FYI
Begin forwarded message:
From: Hector Cintron
Date: December 3.2015 at 3:52:26 PM GMT-4
To: Jermaine Omar Welch
Cc: 'Cecile de Jongh' Alyster Edw
Subject: RE: fiber project
Hi Jermaine,
I just spoke with omar and the cable hasn't arrived, what we can do is this, I'll split the work on two trips, I'll go tomorrow weather permitting (it's supposed to be sunny) regardless if the VINGN circuit is ready and I'll
do the installation. I'll bong up the router and install the 2 switches to be able to monitor the dragonwave and I'll leave the deep inspection and testing for the second trip once VINGN is up.
There will be a downtime of between 1to 2 hours as I make the changes. If this is acceptable I'm a GO for tomorrow. What need after the switch installation is the login for the dragonwave so once this is done I
can start with the verification of the link (no changes will be made).
On the second trip I'll go to the island with Alyster takedown the dragonwave to do the following:
• Test VINGN circuit
• Test VINGN failover
• Verify all grounding
• Verify all connectors weatherproofing
• Verify Lightning arrestors
• Check all cables and replace cables if needed
• Upgrade firmware on DW if needed
• Make configuration changes to the DW if needed
Let me know if this is acceptable.
From: Jermaine
Sent: Wednesday, December 02, 2015 16:31
To: Omar Welch
Cc: 'Cecile de longh% Alyster Edwards; Hector Cintron
Subject: RE: fiber project
Email received from outside of the ATN domain. Use caution before using links/attachments.
Good Evening Omar,
I am following up to verify that VINGN is on target for tomorrow and Choice for Friday.
Regards
Jruan
From: Hector Cant= (maia
Sent: Monday, November 30, 2015 5:11 PM
To: Jermaine Ruan
Cc: Cede de )ongh; Omar Welch; Aster Edwards
Subject: RE: fiber project
Perfect, you got everything. The PDF only had the fiber from Power and Tel and not the items from curvature, so I Just wanted to make sure.
Thanks
From: Jermaine Wan rmailto:
Sent: Monday, November 30, 201517:03
To: Hector Cintron
Cc: Cecile de )ongh; Omar Welch; /doter Edwards
Subject: Re: fiber project
(Tail received from outside of the ATN domain. Use caution before using links/attachments.
Good day/lector
I have 2 simplex and 3 duplex cables from power and tel. I have 1hwic module and 1etc connector.
EFTA01139593
Sent from my Phone
On Nov 30, 2015, at 4:31PM, Hector Ontron wrote:
Those are the fiber able from power and tel, was an order placed for the culvature Items?
Bellow I highlighted the items:
Green are the items from Power and Tel that arrived
Yellow are the items from Culvature that I do not see listed on the PDF
From: lermaMe (mailto:
Sent Monday, November 30, 2015 16:29
To: Hector Critron; 'Cecile de )onoll'
Cc Omar Welch; Alyster Edwards
Subject RE: fiber project
Einar received from outside of the MN domain. Use caution before using links/attachments.
Please see attached
From: Hector Cintron (matt
Sent: Monday, November 30, 2015 12:54 PM
To: Ceole de )ongh
Cc: Omar Welch; lerrnaine, Nyster Edwards
Subject RE: fiber project
lermaine,
Can you send me a list of all the items that you received? I want to make sure we have everything. Utast created a BOM to keep track of what is needed and I'm sure I'll adding to the work/pending list
5O1L1
0111 part desc Installed Location arrived Responsibility
1 CISCO2921/K9 Cisco Router Data Room Installed Choice
1 mcac-o V'NGN Simplex Single Mode Module In the cisco router Data Room (Si
1 SANGN Simplex Cable 35' ST to LC Between Cisco Router and Patch Panel (coming from STT) Data Room LSI
1 HWIC-1GE-SFP wiC Card for SIP Cisco Router Data Room (Si
1 MM_*r cable 6' Sia Between Cisco Router and Patch Panel Data Room LSI
1 GLC-SX-MM MM Fiber Module Cisco Router Data Room x Choice
1 GLC-SX-MM MM Fiber Module Cisco 3560 Building -Gym x Choice
1 IMEI MMINIM Between Cisco 3560 and patch Panel Building -Gym LSI
4 rackmount screws for Cisco 3560 Building -Gym LSI
1 3560G-24 Cisco 3560 Building -Gym x Choice
1 3560G-24 Cisco 3560 Outside Cabinet x Choice
4 rackmount screws for Cisco 3560 Could use existing from netgear Outside Cabinet LSI
Other Pending Items/Work
Cross Connect STT Beach VINGN
Router Config Info X LSI
EFTA01139594
Dragonwave Warrantee Info
Dragonwave Survey Includes Signal, Firmware, Hardware, Monitoring, Grounding Choice
From: Cede de Jongh
Sent Wednesday, November 25, 2015 13:94
To: Hector Caton
Cc Omar Welch; Jermaine
Subject Re: titer project
Email received from outside of the ATN domain. Use caution before using links/attachments.
Thank you Hector.
On Nov 25,2015, at 11:37 AM, Hector Cintron wrote:
I can only comment about 113
3 - it should, this way I can do a fill integration of the VINGN, Dragonwave backup, test (allover.
The plan that I would like to do:
• install VINGN via the new router. Test it and switch the island over this new connection pnmary)
• Once this is done I can takedown the Dragonwave connection to add some switches to be able to monitor the link and take over maintenance. Once this is complete
• Reconnect the Dragonwave as secondary link
• Test (allover to Secondary (OW).
The above plan has a 1-2 min downtime.
If ViNGN is not ready I can still do the install but I need to install the switches needed to monitor the dragonwave there will be a downtime of a few hours as I do the swap but no testing will be done.
Hector.
From: Cede de Jongh
Sent Wednesday, November 25, 2015 10:40
To: Hector &Aron
Cc Omar Welch; Jermaine
Subject Re: fiber paged
Email received from outside of the ATN domain. Use caution before using links/attachments.
Ok.
1. Does this still need to be scheduled with them?
2. If so, do we do that or do you?
3. Does this need to be done before Hector goes to the island or can it be done anytime afterwards?
On Nov 25, 2015, at 10:19 AM, Hector Cintron •: ,• wrote:
The crossover does require a visit to the Pole (the one in St Thomas at the beach) where ViNGN connects to the fiber the goes to the Island.
From: Cede de Jongh
Sent Wednesday, November 25, 201510:17
To: Omar Welch
Cc Jermaine; Hector Ontron
Subject Re: titer project
Email received from outside of the MN domain. Use caution before using links/attachments.
Does this "crossover" require VINGN to visit the site or Is it something that is done remotely from their office?
On Nov 25, 2015, at 10:01 AM, Omar Welch wrote:
Hi Cecile
The connection does play a part in the delay until Monday but not the confirmation for today as no confirmation was made for today. We are assisting ViNGN to be ready for Monday.
'True leaders fortify themselves with thinkers and innovators, because yes men are only saying yes to self preservation?
On Nov 25,2015, at 8:13 AM, Cecile de Jongh - wrote:
Email received from outside of the MN domain. Use caution before using links/attachments.
Good morning Omar and Hector,
Has the date switched to Monday due to the fact that VINGN has not done the crossover? If so, why did Hector confirm today? Will VINGN complete the crossover by Monday?
On Nov 25, 2015, at 9:02 AM, lermaine . - wrote:
EFTA01139595
Good day Omar
I am not understanding Mn. As per my conversation, I stated Monday is too long. I started receiving emails from Hector concerning the installation shortly after. One of my last email was confirming tomorrow.
Jruan
From: Omar Welch a
Sent: Wednesday, November 25, 2015 8:55 AM
To: lermane
Cc: Hector Cintron; Cece de longh
Subject: Re: fiber project
lermaine per my message Hector will not be able to complete installation until Monday please make arrangements for this. Also we are still awaiting confirmation from VINGN on the cross connect.
"True leaders fortify themselves with thinkers and innovators, because yes men are only saying yes to self preservation."
On Nov 24, 2015, at 3:32 PM, lermalne - wrote:
Email received from outside of the ATN domain. Use caution before using links/attachments.
Good Day Hector,
Please be advised, all components are here in the office ready for installation tomorrow. Does VINGN have the crossover in place?
Regards
Jruan
From: Hector Cintron mailto:
Sent Tuesday, November 24, 2015 12:28 PM
To: lermaine Ruan
Cc Omar Welch
Subject: RE: fiber project
Hi iermaine.
Can you send me a list of the items you have for the install? I want to make sure we have everything before I head over there.
Thanks.
From: Hector Cintron
Sent Wednesday, November 11, 2015 10:47
To: lermatne Ruan'
Cc Omar Welch
Subject: RE: fiber project
I cannot give you a date sense it's all based on the following:
? VINGN installs the cross connect
? whether we order the parts or LS1 order the parts. This was something that Omar was going to speak to (sorry I do not know the name) LSJ Finance.
o For VINGN connection (Router Module, Fiber Module, Fiber cable)
o Choice connection (switches, fiber cables)
Also just an FYI I'll be going on vacation staring this Friday and I'll be back on Monday 23rd so assuming all the above is installed, purchased and delivered by the time I get back it would be sometime the week
of the 23rd
Hector.
From: lermame Ruan [maslto ]
Sent Wednesday, November 11, 2015 09:52
To: Hector Ontron
Cc Omar Welch
Subject: Re: fiber project
Erna,' received from outside of the ATN domain. Use caution before using links/attachments.
Good morning gentlemen
The principal is requesting a new date for the fiber. Do you have a suggested estimated time of completion?
Regards
Jruan
Good evening all
When is the new date for the connection so I can update my superiors
Regards
Jruan
Sent from my iPhone
EFTA01139596
On Nov 10, 2015, at 11:25 PM, Hector Cannon -- wrote:
Hi Guys,
I haven't received notifications that the items that we need to finish came in so that would be no.
From: Omar Welch
Sent: Tuesday, November 10, 2015 19:06
To: .1emaine Ruan; Hector Ontron
Subject: Re: fiber project
Hector?
'True leaders fortify themselves with thinkers and innovators, because yes men are only saying yes to self preservation."
On Nov 10, 2015, at 6:44 PM, 'ermine Ruan ea- wrote:
Email received from outside of the ATN domain. Use caution before using links/attachments.
Good night Omer
Yep, I am trying to line up the runs in the morning
Regards
Jruan
Sent from my (Phone
On Nov 10, 2015, at 6:19 PM, Omar Welch wrote:
To come to the Island?
'True leaders fortify themselves with thinkers and innovators, because yes men are only saying yes to self preservation."
On Nov 10, 2015, at 6:10 PM, lermaine ffi wrote:
Email received from outside of the MN domain. Use caution before using linkstallachinents.
Good day omar
Is hector still on for tomorrow?
Regards
Jruan
EFTA01139597
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 119ad6c4-b567-404a-8bf1-28af40767905
- Storage Key
- dataset_9/EFTA01139593.pdf
- Content Hash
- c073079833e0fdbdd46e473249efaad0
- Created
- Feb 3, 2026