From: David Mitchell
Sent: Wednesday, May 2, 2018 12:31 PM
To: Jeffrey Epstein
Update on TCO , working completing this list TODAY
Please see the below sign offs needed for Grant to complete the TR1 forms, which will be the remaining paperwork to
obtain TCO for 19 West 31 Street <x-apple-data-detectors://0> . Grant has requested the below in order to complete the
Till forms:
1. Structural - the walls/ceilings closed up, not possible for an inspection; therefore, need the structural engineer to sign
off on all nonconformities. The structural engineer needs to approve work completed. EWA WORKING ON LIST
2. Sprinkler system - no submittals on site / The MEP engineer needs to sign off on the installed sprinkler heads and
confirm the installed sprinkler heads were per the submittals. GRANT CONFIRMING LOCATION OF PHOTO
3. Masonry anchors - the walls/ceilings closed up, not possible for an inspection; therefore, need the structural engineer
to approve the SOP conditions and if possible, have the GC provide photos and info on installation. EWA TO CONFIRM
4. Fenestration - need an email confirmation from architect stating that the U-factor, R values, and insulation of field
work conforms to specifications.
5. Fire protection • need the DOB / FDNY sign offs from Metropolis/ACP Electrical.
6. Mechanical - then one last item, Grant inspector needs to do the final Mechanical inspection.
DAVID MITCHELL
Mitchell Holdings LLC
745 Fifth Avenue
New York NY 10151
USA
EFTA_R1_01554616
EFTA02453650
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 1183600c-1928-4b38-9580-060962478243
- Storage Key
- dataset_11/EFTA02453650.pdf
- Content Hash
- 84c24007a96c1922aae1d3182f6a7ad4
- Created
- Feb 3, 2026