Zorro Projects - 6/29/13
Landscaping (22) - Start End Total Est. Cost
Rear Planter Bed Notes Photo
6/1/13 $75,000.00 3/28/13 - Refurbishment & Maintenanc
Front & Rear Parking Beds e proposals from 3
companies forwarded to RK & DI
Bowel Garden
4/27/13 - JE approved Aspen Landscaping for Refurbishme
Aspen Grove nt
15/9/13 - New proposal forwarded to JE & RK, awaiting
Pinion Screen direction
5/16/13 - Final proposal forwarded to RK, will discus
s with JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started
6/8/13 - Work continues, soil preparation in progress
6/14/13 - Plant material starting to arrive, more due next X
week
6/18/13 - More plant material arrived
6/21/13 - Planting & Irrigation complete at back parkin
g area.
6/22/13 - Planting & Irrigation continues around chess
set -
attached photos
6/26/13 - More plant material arrived on site
6/27/13 - Preparation front parking area begins, Colum
bians &
Trumpet Vine planted along pathway between MI-I & Dog
Pen.
Irrigation installed in all planted areas - attached
photos
landscape Lighting Timers Replacement - Start End I Total Est. Cost Notes Photo
4/27/13 - JE approved
i5/1/13 - Unable to move forward until Project 22 - Landscaping
has been resolved
6/1/13 - Brice to review with Aspen about location
etc.
6/7/13 - Awaiting electrical proposal due 6/29/13
Landscaping - In House - Start t
End Total Est. Cost Notes
Ponderosa Pines at Front Entrance & 6/3/13 !Photo
4/27/13 - JE approved the removal of dead pine in courty
Landscape Lights at MH ard &
Ponderosa Pines, Landscape Lights & relocate Pinions to
the area.
6/3/13 - Project Started
'6/7/13 & 6/18/13 - Removal of Ponderosas & Pine comp
lete
6/25/13 - Work to begin on landscape lighting
6/29/13 - Have installed landscape lighting where planti
ng is
complete, will continue next week
EFTA01124657
Zorro Projects - 6/29/13
Terraces (27) - Three B's Start End Total Est. Cost Notes
Terraces - $52,000.00 4/7/13 Photo
$56,200.00 12/12/12 - Bid Received
Stucco/Gutters/Painting - $4,200.00
3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of mater
ial, vendor
ihas reordered, will recover area once on site.
6/7/13 - Material on site, will continue 6/10/13
6/14/13 - Membranes & Gutters Complete - attached
photos
6/18/13 - Stucco & Painting scheduled to start
6/21/13 - Stucco & Painting Complete - attached photo
s
16/24/13 - Final review of completed work
7/2/13 - Final Punch Out to begin of all outstanding
work
Front Gates Openers Call Boxes (30) - Start End Total Est. Cost Notes Photo
4/20/13 - Bid received, requested vendor to make adjust
ments
5/9/13 - Received revised bid. Options & Equipment review
ed
5/12/13 - Options & Equipment selected, final bid due
5/21/13
5/21/13 - Final bid received via fax, unable to read, vendo
r will
resend.
6/8/13 - Final bid attached, also forwarded separately
to RK.
i6/11/13 - RK requested material breakdown
6/14/13 - Material breakdown forwarded to RK
6/19/13 - Resubmitted revised pricing to RK - awaiting
direction
6/28/13 - RK requested that Three B's submit an estima
te for this
work. Have contacted Three B's, will be on site next week
to
review
EFTA01124658
Zorro Projects - 6/29/13
Cooling Tower (36) -113H Start End Total Est. Cost Notes Photo
4/24/13 - RK approved bid from SPX & JBH. RK has all cost
details
5/3/13 - Deposit was to be forwarded, awaiting confirmatio
n
6/20/13 - Unit on site - attached photo
6/21/13 - Noting attached E Mail, JBH have pulled their
team off
moving forward with this project until RK makes conta
ct about
outstanding balance
Payment received by Vendor
7/8/13 - Installation scheduled
Replacement of Pool Pac (33) - Start End Total Est. Cost Notes
Engineering Inspection - $9,100.00 9/11/12 Photo
4/29/13 - Quote forwarded to RK, who requested more detail
Unit Cost - $43,170.00
5/8/13 - Revised quote forwarded to RK, awaiting direct
Camera Ducting Inspection - $1,214.91 ion
5/22/13 - Beaudin Ganze on site to review project
Ducting - TBA
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera.
16/3/13 - JBH forwarded estimate
6/4/13 - JE approved moving ahead
6/11/13 - JBH due on site
6/12/13 - JBH on site, completed camera inspection, awaiti
ng
report/disc.
6/21/13 - Report/Disc forwarded to Beaudin Ganze, awaiti
ng
report
7/8/13 - Report due 7/8/13
Repair Pool/Spa (29) - Start End Total Est. Cost Notes
$12,600.00 5/9/13 - Vendor on site
Photo
5/16/13 - Bid breakdown forwarded to RK
iJE requested work be completed in Sept
EFTA01124659
Zorro Projects - 6/29/13
Water Sample of Tap Water- Start c End Total Est. Cost Notes Photo
6/12/13 4/27/13 - JE requested water samples be taken.
This will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/2/13 - All Wells up and running
6/12/13 - Water samples taken. Results due back 7/3/13
Exterior Doors Main House - Three B's Start End Total Est. Cost Notes Photo
4/27/13 -JE requested that all saddles on exterior doors be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
7/2/13 - Final Punch Out to begin of all outstanding work
Audio Upgrade - in House Start End Total Est. Cost Notes
New TV's 6/3/13 Photo
Installed - final programming required
DVD Players/Theater Upgrade
Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before movin
g
forward
5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Breakfast Rm, Lodge & BH
6/12/13 - Gym, Lodge & BH Systems Complete
6/14/13 - Will exchange the Samsung DVD for a Marantz DVD
in
Breakfast Rm
6/22/13 - Awaiting delivery of Marantz DVD
6/27/13 - Unit has shipped
Kitchen Table Electrical - (35)- Three B's Start End Total Est. Cost
Electrical & Data Cut In - $2,160.00 Notes Photo
6/3/13 3/1/13 - Bid received Lead Time 1 Week
6/3/13 - Project Started
6/7/13 - Under floor conduit due to be completed 6/12/13
6/13/13 - Conduit installed, tiles replaced & grouted. Cat 5 still
to
be pulled and punched down
EFTA01124660
Zorro Projects - 6/29/13
Media Room Curtains (24) - Start End Total Est. Cost Notes
Blackout & Rings '2/24/13 photo
$6,262.08 4/27/13 -JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) - Start End Total Est. Cost Notes
Lined & Rings 2/24/13 Photo
$2,527.01 4/27/13 -JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enough yarda
ge
I of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
gym - Mirrored Doors - Three B;., Start End Total Est. Cost Notes
2/24/13 Photo
3/4/13 - Project Complete. JE requested further work, which
will
begin once Project 27 - Terraces complete
7/2/13 - Final Punch Out to begin of all outstanding work
Phones Main House (31) - Start End Total Est. Cost Notes Photo
4/27/13 - JE approved installation of new phones at MH
Awaiting for service provision & estimated cost of delivery of
services - Project 21Microwave & IT
6/22/13 - Awaiting response from Southwestem Wireless
on FCC
License Application & Router at MH
6/28/13 - Requested RK to forward deposit
Phones Ranch Central (35)- Start End Total Est. Cost Notes Photo
6/21/13 - Will forward proposal for phone system by 6/28/1
3
6/27/13 - Project On Hold until Microwave solution resolv
ed
EFTA01124661
Zorro Projects - 6/29/13
Microwave & IT -(21) - Start End Total EA. Cost Notes Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE, RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann reference
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded details of RSM Craig
Franck. Brice has been in contact with Craig will forward detail
s
5/24/13 - Received bid from Southwestern Wireless, have call
set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK & JR
6/8/13 - Forwarded TW Telecom Proposal for Delivery of Servic
es
to JE & RK. Firm Bids due by 6/14/13
6/14/13 - Received bid from Southwestern Wireless, confirming
details before forwarding
6/15/13 - informed JE, will forward once all details confirmed
6/20/13 - JE approved South Western Wireless bid. RK to
negotiate final bid
6/27/13 - Southwestern Wireless unable to delivery bundled Tl
6/28/13 - Looking into options
Cell Repeaters & Wi-Fi - In House Start End Total Est. Cost Notes
Cell Repeater - Library Photo
Will have installed when time allows
Cell Repeater - Gym
Will have installed when time allows
Computers - Start End Total Est. Cost
Lap Top - Lodge Notes Photo
Requesting Approval to Purchase
Desk Top - RC Office
Requesting Approval to Purchase
Well K (37)- Start End Total Est. Cost
Plugging First Hole Notes Photo
$15,000.00 Estimate to plug 1st hole
Lodge Roof Start End Total Est. Cost
Repair/Replace Broken Sections Notes Photo
Three B's will complete after summer visit
EFTA01124662
Zorro Projects - 6/29/13
Yurt - (23) - Start End Total Est. Cost Notes
Replacement Walls/Roof/Door/Windows 5/9/13 !Photo
$6,355.00 4/27/13 - JE approved investigating options
plus shipping 5/9/13 - Project Request forwarded to
RK & JE
charges of 5/9/13 -JE approved Project, awaiting direct
ion on deposit
approx. payment from RK
$480.00 5/13/13 - Deposit forwarded to vendor $3,177.50
Removal of furniture, deconstruction of existing
walls/roof/windows & door. Then reconstruction of base,
resanding/sealing floor required -in house
7/3/13 - Scheduled Ship Date
Repair/Painting Work- Ion Start End Total Ed. Cost Notes Photo
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work
that
will be required after MBR Terrace is completed.
6/29/13 - Additional work - sign on Adobe
Painting/Staining/Sealing - In House Start End Total Est. Cost Notes
Stables - including outside/inside lights Photo
Work to begin once MH projects complete
Adobe - including wooden deck & front
Work to begin once stables complete
Log Cabin
Work to begin once all painting/staining projects complete
at RC
Lodge
Work to begin once all painting/staining projects comp
lete at RC T
Reservoir
Work be begin once all painting/staining/sealing projects
complete
Fuel Storage Tanks
Work to begin once all painting/staining/sealing projects
complete
RC Office Interior
Work scheduled for Winter
RC Mechanical Bays - interiors
Work scheduled for Winter
RC Garages - interiors
Work scheduled for Winter
EFTA01124663
Zorro Projects - 6/29/13
Ext Doors Main Compound - In House Start End Total Est. Cost Notes Photo
Front, Estancia, Mech, Garage, Pool Doors 6/24/13 6/28/13 $60.00 6/24/13 - Project Started - refurbish & waxing all wooden doors
6/28/13 - Project Complete - attached photos X
Fuel Storage Tank Area - In House Start End Total Est. Cost Notes Photo
Removal of grass. Matting & edging to be
installed
Gravel/Edge Work RC Paths - in House Start End Total Est. Cost Notes Photo
All paths to be dug out, edged and gravel
to be installed
-- I
Log Cabin - In House Start End Total Est. Cost Notes Photo
Step Outside - Repair/Replace Broken
Section
Caboose -In House Start End Total Est. Cost Notes Photo
Installation of Retaining Wall To begin early Fall
4 Bay Garages - In House Start End Total Est. Cost Notes Photo
Repair Leaking Roof To begin early Fall
Repair Damaged Wall
Pole Barn Water Truck Parking Start End Total Est. Cost Notes Photo
Installation of a Retaining Wall To begin late Fall, Early winter
Cattle Gates/Guards x 3 - In House Start End Total Est. Cost Notes Photo
Refurbishment, Empty & Paint To begin early Fall
Cactus Removal - In House Start End Total Est. Cost Notes Photo
To begin late Fall, early Winter
Tilt Trailer - In House Start End Total Est. Cost Notes Photo
Refurbish/Paint Winter Project
EFTA01124664
Zorro Projects - 6/29/13
Vehicles Start End Total Est. Cost Notes
2013 Ford Expedition - review Captain 3/27/13 Photo
5/2/13 - Estimate received - $11,528.74
Seats to be Installed
5/31/13 - as of date unable to get a 2nd estimate,
I
ft E Start End Total Est. Cost Notes Ph
oto
4/27/13 - JE approved investigating purchase of 2 dogs.
Researching
Inventorv/dean Work Shops -In House Start End Total Est. Cost Notes
6/6/13 Photo
6/20/13 - Landscaping, Paint & Wash Bay 90% complete -
attached photos. All these location will be painted over the winter
6/21/13 - Work continues as time allows - complete clean up
&
inventory of all work shops at RC & MH
6/29/13 - Landscaping, Paint, Irrigation & Wash Bay Complete.
Welding, Woodshop, Mech Shop 80% complete
Purchases Start End Total Est. Cost Notes
Outside Pool Furniture Photo
Investigating Options
Pool Pace Clock
7/10/13 - Due on site
Large Chrome Pool Clock
Investigati Options
Facial Machine
to purchase
Wells - Dakota & K
Combined Usage as of date 6/14/13
8.03 afa
2014 Budget
Bunkhouse Start End Total Est. Cost
Window/Doors - Total Replacement Notes Photo
EFTA01124665
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 0a499b1d-6bab-4c0d-a45c-8c07679abfd8
- Storage Key
- dataset_9/EFTA01124657.pdf
- Content Hash
- b70228c2e7cd8178ff4ef3fb3da94d81
- Created
- Feb 3, 2026