Yes
On Fri, Sep 14, 2018 at 10:40 AM, Richard Kahn < > wrote:
Gilbert is projecting finish date of October 17th
Brice stating that he needs to inspect grade at garages....seems silly if we have testing agency...
should i ask to review third party testing reports to date and compare to areas larry mentioned were bumpy?
please advise
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York, NY 10022
tel
cel
Begin forwarded message:
From: Gilbert Luna <I
Subject: Re: Zorro Ranch Asphalt Paving
Date: September 14, 2018 at 10.24:18 AM EDT
To: Richard Kahn
Cc: Beto Sanchez
Richard,
We had the asphalt plant to ourselves on Wednesday and were able to place 1,096 tons of asphalt on the road
from the house. We are now about 1/4 mile away from the cattle guard where the road turns back to the ranch
complex. We are currently lowering the grade at the equipment storage shed and regrading the garages area
to accommodate drainage. Brice has asked us to call him prior to paving this area so he can fly out and
inspect the grade. I drove over the completed asphalt at 30 MPH and the ride seemed good except for one
transverse joint where the next day's paving started. We will repair the joint to improve the smoothness of the
roadway. I spoke with the Lab Director of the third party testing agency ( BSN Santa Fe ) yesterday and he
confirmed that the testing for materials and densities is going well so far. With good weather, we are
projecting a finish date of October 17.
Thank you,
On Thu, Sep 13, 2018 at 7:04 AM, Richard Kahn < > wrote:
can you please call me today to review job
thank you
EFTA01023165
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York, NY 10022
tel
fax
cell
On Aug 31, 2018, at 10:52 AM, Gilbert Luna < > wrote:
Good morning Richard,
The weather was dry this past week and we made good progress. On Tuesday we made repairs to the
existing asphalt pavement at the entrance to the house in preparation for resurfacing. Wednesday and
Thursday were spent paving ( 1,120 tons ) and we are now about 3 / 4 mile away from the house with
asphalt, one mile away with gravel, and about 1 1/2 miles away with grading. We will be off on Monday
for Labor Day and return on Tuesday to work 4-tens through next Friday. Attached is our progress billing
for the month of August.
Thank you,
On Thu, Aug 23, 2018 at 5:13 PM, Richard Kahn < wrote:
happy to hear things are going well
thank you for update
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York NY 10022
tel
fa
cel
On Aug 23, 2018, at 6:31 PM, Gilbert Luna < wrote:
Richard,
The grading crew has gone about a mile south of the house with grading and base course application.
As of today, 1,016 tons of gravel base course has been delivered and spread. To improve efficiency,
EFTA01023166
the crew switched to 4-10 hour days this week and thus will not be working tomorrow. We will
resume Monday with grading and gravel. On Tuesday, the existing asphalt road at the house will be
repaired to receive an asphalt overlay. We have scheduled our first delivery of asphalt for next
Wednesday to start paving the prepared roadway south of the house. Afternoon rain showers are a
nuisance to our work but they haven't slowed us down too much. Besides, the rain is good for the
ranch!
On Thu, Aug 23, 2018 at 1:04 PM, Richard Kahn < wrote:
thank you for update last week
can you please send weekly updates every thursday or friday
thanks
Richard Kahn
HBRK Associates Inc.
75 Lexington Avenue 4th Floor
New York NY 10022
fax
cel
tell
Begin forwarded message:
From: Gilbert Luna <I
Subject: Re: Zorro Ranch Asphalt Paving
Date: August 16, 2018 at 6:45:09 PM EDT
To: Richard Kahn sc >
I just returned from the ranch. Our grading crew is working on the stretch of road south of the
house getting it ready to receive gravel and then asphalt. A couple of crew members were setting
grade stakes at the center of the road and each shoulder to insure proper slope. Our 3500 gallon
water truck was filling up at the western well in about 15 minutes. Mobilization is completed
and the weather was good today.
On Thu, Aug 16, 2018 at 1:30 PM, Richard Kahn < wrote:
can you please provide an update on how project is progressing
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York, NY 10022
tel
fax
cel
I
EFTA01023167
On Aug 9, 2018, at 4:02 PM, Gilbert Luna <Ila wrote:
Richard,
Attached is our revised proposal, without the well house road, in the amount of $ 635,000.00
plus tax. Also, attached is our invoice for the down payment at 40 % plus tax, and wiring
instructions for our account at Wells Fargo Bank. I have not included the sketches mentioned
in our proposal that were previously sent to Mr. Gordon, but they can be sent if you need
them. We are scheduled to start next week but we are able to postpone for a week if that's
more convenient for Mr. Epstein. Let us know.
Thank you,
On Wed, Aug 8, 2018 at 10:34 AM, Richard Kahn < > wrote:
we are approved to proceed at 650,000 however we would like to remove road to well
house so adjusted net price will be 635,000 as you told me that additional road was 15,000
can you please revise quote with new price of 635,000 and scope change then resend along
with wiring instructions unless you prefer us to fed ex our deposit check of 40%
also we will pass on bond but would like to proceed with testing
thank you
Richard Kahn
HBRIC Associates Inc.
575 Lexington Avenue 4th Floor
New York NY 10022
tel
fax
cell
Begin forwarded message:
From: Brice Gordon <
Subject: Fwd: Zorro Ranch Asphalt Paving
Date: July 31, 2018 at 1:18:26 PM EDT
To: Rich Kahn <
Cc: Zorro Ranch <
as requested
Forwarded message
From: Gilbert Luna <I
Date: Tue, Jul 31, 2018 at 1:16 PM
Subject: Zorro Ranch Asphalt Paving
EFTA01023168
To: Brice Gordon
Cc: Matt Luna
Hello Mr. Gordon,
Attached is our proposal for the asphalt paving improvements at Zorro Ranch. Our
schedule would be to start on August 13, 2018 and complete the work in eight weeks.
Our price is based on purchasing the asphalt mix from Mountain States Constructors in
Moriarty, NM. They have a hot mix asphalt plant set up there to take care of the paving
project on NM 41 by the ranch. However, they can not guarantee that the plant will still
be there after October, so it is imperative to get started on the project soon. The cost of
asphalt cement has been rising lately and to bring in material from our regular supplier in
Albuquerque would add approximately $ 40,000.00 to the cost. Our payment terms are
as follows: 40% down payment upon mobilization. Monthly pay requests submitted on
the 30th for percentage of completion of the balance ( Net 15 days ). Final billing of 5%
of the contract amount due upon inspection and acceptance by you. Thank you for your
consideration and please contact me if you have any questions.
Regards,
Gilbert A. Luna
President
www.utinm.cont
3825 Academy Parkway North,
Albuquerque. V.I1 87109
Cell P
Phom
Fax: .)
Brice Cordon
Stanley, NM
LSJ-GSJ, USVI
Ph
EFTA01023169
;2,
Gilbert A. Luna
President
wwmucinm.com
3825 Academy Parkway North, NE.
Albuquerque NM 87109
Cell P
Phone:
Far: S
CZorro evise oposal.pdfxWire Transfer Instructions.pdf,Corro Ranch Down
Payment Invoice.pdf>
Gilbert A. Luna
President
www.ucinm.com
3825 Academy Parkway North, N.E.
Albuquerque. NM 87109
Cell P
Phon
Fax:
Gilbert A. Luna
President
www.ucinm.com
3825 Academy Parkway North,M
Albuquerque, NM 87109
Ch P e 7
Phon
Fax:
EFTA01023170
Gilbert A. Luna
President
www.ucinm.com
3825 Academe Parkway North, N.E.
Albuquerque, 87109
CellP
Phan
Fax: i
<Zorro anc r ugus Invoice.pdf>
a
Gilbert A. Luna
President
wwwvucinm.com
3825 Academy Parkway Nortit.M.
Albuquerque. ASH 87109
Call I'
Phone
Fax: .
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation@gmail.com, and
EFTA01023171
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA01023172
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 08bb0b0d-9510-4976-a471-754a2a882f8b
- Storage Key
- dataset_9/EFTA01023165.pdf
- Content Hash
- 427a24865ed54314c1b314054c8008b3
- Created
- Feb 3, 2026