LSJ CONSTRUCTION
Subcontractor Payout
Project: Mechanical Building #1002 October 19, 2010
Trade: Plumbing, Fire Protection
Requisition #02
Subcontractor Abbott & Lineham Mechanical
Insurance ex iration: March 26. 2011
nvoice # Requisition #02
Phase # 15-400, 15-500
Original Contract Sum: $287,100.00
Change Orders Submitted & Approved: $0.00
New Change Orders: $0.00
Total Work Contracted to Date: $287,100.00
Total Work Completed to Date: J 78% $224,833.50
Less Retainage: $11,241.68
Total Payments Made to Date: $71,912.15 / it
Total Current Payment Due: $141,679.68 t/OF.
Balance to Finish including Retainage: $73,508.18
Sales Tax Liability:
a. Subcontractor/Supplier is liable, explaiiinstall only / tax
included in contract
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company:
d. Shipping None
Total Outlays for this contract incl. Sales or Use Tax: $224,833.50
JEE approval attached Invoice Attached
YES NO YES NO
X X
Submitted Bill Approved by: Gary
Signed: Signed:
Date: October 19, 2010 Date: October 19, 2010
Approved by: Emad Approved by:
Signed: Signed:
Date: a Ito Date:
EFTA00722183
Emad Hanna
From: Monique Harry [
Sent: Wednesday, Oc ober 20, 2010 12.41 PM
To: Emad Hanna
Subject: Abbott and Lineham Mechanical
Attachments: Abbott Req 1 1002 Fuel Piping.pdh Abbott Plumbing 1002 Req 2.pdf
Emad,
Attached for payment (2) Abbott and Lineham Mechanincal Payouts $164,289.68.
Plumbing, Fire Protection
1002 - 15-400 - $14,725.00 vC.
1002 - 15-500 - $126,954.68 I,-
Fire Piping
1002 - 15-310 -$22,610.00
Monique
EFTA00722184
I.SJ CONSTRUCTION
Protect Mechanical Building #1002
ubcontraclor - Full logal name: Abbott R I inellam Mechanical Dabs Revised October 19. 20W
Phase # 15-400. I 5-500
Trade: Plumbing. Fire Protection
Invoice N. Requisition #02
Insurance expiration: 26-Mar-t I Payment
Partial Final
X
Invoice/RG.O Date CK) Antoine Iii:iairinge Due Paid Date Paid Clash!!
Contract Amount 03/15/1 787 in
COtll
C0112
CO/t3
0014 -
CO#5
Requisition tit 05/26/10 Fins Protection 75.897.00 3.11, 912.151
7 71.912.15 0.00
Requisition #2 10/19/10 File Protection 149136.50 II 679.68 mi 07968
Requisition 03 0.00
Requisition #4 0.00
Requisition #5
Requisition #6
Requisition it/
Rexpesition att _
Requisition #9 0.00
Total 22-183350 11.241 68 213.59183 /1.917 is I41.67858j
Contract Amount Phase
Contract Plumbing. Fire Piotechon 28/.100 00
CO#1 DescriEUOn
CON2 Desaletkin
CO#3 I Mscriplion
CO#4 I inscription
CONS Description
Contracted to Date I 28/.10000
Balance of C.ontract wiRetainage 73.508.18
EFTA00722185
Abbott & Lineham Mechanical
6501 Red Hook Plaza STE 201
St. Thomas, VI 00802
Tel: Fax:
Invoice
10/19/10
LS1, LLC
Attn: William Rowles
6100 Red Hook Quarter B-3
St. Thomas, VI 00802
Wet Sprinkler System —Mechanical Building Requisition #2
Quote: $161,600.00
Contract #1002 Agreement #1
'Cost Code: 15-500
Previously billed: Req. #1 $25,000.00
Pump and controls $25,000.00
Current due: Req. #2 $79,360.00
Balance on main pump and controls $35,000.00
Materials on site 70% $21,000.00
Piping labor @ 20% $ 8,000.00
Profit and overhead $15,360.00
Current due less 5% retainage ($3,968.00) $75,392.00
EFTA00722186
Abbott & Lineham Mechanical
6501 Red Hook Plaza STE 201
St. Thomas, VI 00802
Tel: Fax:
Invoice
10/19/10
LSJ, LLC
Attn: William Rowles
6100 Red Hook Quarter B-3
St. Thomas, VI 00802
Water Pumps—Mechanical Building Requisition #1
Quote: $134,920.00
Contract #1002 Agreement #1
( Cost Code: 15-400
Current due: $15,500.00
50% deposit on pump
Current due less 5% retainage ($775.00) $14,725.00
EFTA00722187
Abbott & Lineham Mechanical
6501 Red Hook Plaza STE 201
St. Thomas, VI 00802
Tel: Fax:
Invoice
10/19/10
LSJ, LLC
Attn: William Rowles
6100 Red Hook Quarter 6-3
St. Thomas, VI 00802
Foam system for oil storage building Requisition #2
Quote: $127,000.00
Contract #1002 Agreement #1
Cost Code: 15-500
Previously billed: Req. #1 $50,697.00 /77i/71-
Design of system $2,500.00
Deposit on foam system $28,197.00 / cY" 7Pi
Pipe and fittings on site $20,000.00
/Ma
Current due: Req. #2 $54,276.50
Balance on foam equip $28,197.00
Piping @ 75% $21,079.50
Profit & overhead @25% $ 5,000.00
Current due less 5% retainage ($2,713.8a) $51,562.70
' <(Z
EFTA00722188
Entities
0 total entities mentioned
No entities found in this document
Document Metadata
- Document ID
- 04c550e1-cc1e-4d86-8698-944a0ae8d834
- Storage Key
- dataset_9/EFTA00722183.pdf
- Content Hash
- eb4f26dd28a6991886e8cc958c695bee
- Created
- Feb 3, 2026